Government Accountability Office: Immigration Detention: ICE Should Determine Cost Effectiveness of New Initiatives Before Continuing
The text Dorworth News extracted from the kept copy
Download the original (PDF, 6.4 MB)
- Fingerprint
- c83e716e131743764e491ef871513e72cac2925b33c4b8e71df621d8efc6bf07SHA-256 of the kept copy exactly as received.
- Original
- https://www.gao.gov/assets/gao-27-108665.pdf
- The text
- 478 paragraphs, read from the kept copy, kept . The words are the document’s own; the layout is the site’s. Its words are read line by line across each page; columns, tables and pictures are not kept here.
Page 26 of the original
BOP facilities. The nine BOP facilities ICE utilized in April 2026 had a median bed rate of $180, the highest of any facility type. These rates ranged from $110 at Federal Correctional Institution Leavenworth in Kansas to $360 at Federal Detention Center Honolulu in Hawaii. Rates were consistent between 2025 and 2026 at the eight BOP facilities ICE used in both years. According to ICE officials, these are the same rates that BOP calculated to house individuals pending trial or serving sentences for federal charges. ICE did not have the ability to negotiate these rates since it is absorbing BOP’s costs for housing Bed Rates at Florida-Funded Immigration detained noncitizens. Detention Facilities • Contract detention facilities and contract-operated service The state of Florida also funded two detention facilities that ICE used in fiscal years 2025 processing centers. These facilities had median bed rates of $151 and 2026. ICE did not enter into a contract or 29 and $126, respectively, in April 2026. According to ICE officials, bed agreement with Florida to operate these facilities as immigration detention centers. rates at contract-operated facilities can be higher than other facility However, the Federal Emergency types because they follow more stringent detention standards than Management Agency (FEMA) awarded a other ICE facilities and may provide more medical services. Officials $608.4 million grant to Florida to support immigration detention. As of October 2026, also said that contractors’ expected rate of profit may also contribute FEMA had reimbursed Florida about $93 to higher bed rates. million for operations at the recently constructed Florida Soft-Sided Facility, also Contract detention facility bed rates can also be subject to annual cost known as “Alligator Alcatraz”. The bed rate at increases negotiated at the time of the contract award to account for this facility is $249 per noncitizen per day, nearly three times higher than ICE’s median factors like wage increases and inflation. ICE data show that bed bed rate of $92. rates increased at 12 of the 21 contract detention facilities and service Florida also requested to use the grant to processing centers ICE used from September 2025 through April support Baker Correctional Institution, a brick- 2026, with most rates increasing by between 1 and 7 percent. Of the and-mortar facility. FEMA approved this request and has reimbursed Florida for remaining nine facilities, eight maintained the same rate and one expenses at this facility at the same $249 bed decreased its rate. rate. See appendix III for more information Source: Documentation and responses from FEMA officials. | • U.S. Marshals Service riders and IGSA facilities. These facilities GAO-27-108665 had median bed rates ranging from $85 to $103. ICE officials said that
29We calculated median bed rates using ICE’s reported bed rate data for each facility as of April 2026. However, actual bed rates may vary depending on the structure of the individual contracts, which may include some costs for services under separate line items.
Page 21 GAO-27-108665 Immigration Detention
Page 27 of the original
the state and local partners who operate most of these facilities are not profit-seeking. ICE data show that 190 of the 232 facilities operated through U.S. Marshals Service riders and IGSAs from September 2025 through April 2026 maintained the same bed rate in that period.30
These trends are consistent with our previous reporting that contract detention facilities and service processing centers had higher median bed rates than facilities with U.S. Marshals Service riders or IGSAs in fiscal year 2019.31 In addition to facility type, ICE officials said that bed rates can be influenced by factors such as unique operational requirements, local pay rates, and facility-wide costs, including rent or maintenance.
ICE’s Expanded and As ICE expanded its detention space throughout fiscal years 2025 and Planned Detention 2026, it often acquired and planned for facilities with relatively high costs. Specifically, the number of facilities where ICE makes guaranteed Portfolio Includes High-payments for a fixed number of beds increased during that period and Cost Facilities ICE has underutilized thousands of those beds, leading to millions in estimated payments for unused beds. ICE also utilized high-cost facilities located on military installations. As discussed previously, ICE also spent about $1.07 billion to acquire 11 warehouses, the majority of which it plans to sell, as well as four facilities it was previously utilizing for about $2.2 billion.
ICE Committed to Pay for an From October 2022 through April 2026, ICE awarded an increasing Increasing Number of Fixed number of contracts and agreements that require it to make guaranteed Beds payments for a fixed number of beds, regardless of whether those beds are filled.32 We previously reported that guaranteed payments protect facility operators from financial loss and can save money when structured to include lower-priced bed rates if ICE uses more than the fixed number
30Of the remaining 42 facilities, 13 increased their bed rates by up to 10 percent, 18 increased their rates by 11 to 49 percent, nine increased their rates by 50 percent or more, and two decreased their rates.
31GAO-21-149.
32Agencies award indefinite delivery and indefinite quantity contracts when the exact quantities and timing for products or services during the contract period are unknown at the time of the award. These contract types require agencies to order, and the contractor to provide, a specified minimum quantity of supplies or services. See Federal Acquisition Regulation §§ 16.501-1, .501-2, 16.504, 48 C.F.R. §§ 16.501-1 (definitions), .501-2 (general; three types of indefinite delivery contracts), 16.504 (indefinite quantity contracts).
Page 22 GAO-27-108665 Immigration Detention
Page 28 of the original
of beds, according to ICE guidance.33 Further, we reported that these payment structures help ICE secure detention space when it has an urgent need and limited options, according to ICE officials.34
However, guaranteed payments also present the risk of ICE paying for beds it does not use. According to agency data, ICE committed to pay for 46,688 fixed beds across 64 facilities as of April 2026, an increase from prior years.35 From October 2025 through April 2026, the average daily population at more than a third of those facilities did not meet the fixed number of beds, amounting to a daily average of 9,733 empty beds that ICE was required to pay for.
For example, table 3 identifies five facilities with a large number of fixed beds that ICE acquired after fiscal year 2024. The average daily population of detained noncitizens at four of the five facilities from October 2025 through 2026 was lower than the fixed number of beds. As a result, we estimate that ICE paid millions of dollars per month for empty beds at these facilities.
33We reported on guaranteed minimum payment structures that require ICE to pay a daily rate for each guaranteed bed. More recently, ICE has adopted a facility operating charge structure at some facilities that requires it to pay a flat monthly fee for all guaranteed beds. In some instances, ICE pays both a flat monthly fee that covers facility-wide expenses and a bed rate that covers the care of each detained noncitizen. For the purposes of this report, we refer to these three structures collectively as “guaranteed payments” because they all require ICE to pay for a fixed number of beds.
34GAO-21-149.
35ICE had 48 facilities with guaranteed payment structures in both fiscal year 2023 and 2024 and 53 facilities in fiscal year 2025, with the number of fixed beds ranging from 27,488 to 32,890 during those three years.
Page 23 GAO-27-108665 Immigration Detention
Page 29 of the original
Table 3: U.S. Immigration and Customs Enforcement (ICE) Guaranteed Payments and Average Daily Populations at Five Recently Acquired Facilities, April 2026
Estimated amount ICE Average daily paid per Fixed number population, Empty fixed month on Facility of beds ICE Daily rate per Flat monthly fiscal year beds per day average for Facility Name pays for fixed beda feeb 2026 (partial)c type on average empty beds
California City CDF 2,560 $40 $ 7,533,333 1,353 1,207 $ 5,020,527 Correctional Facility
North Lake CDF 1,800 $15 $ 6,118,689 1,378 422 $ 1,627,051 Correctional Facility
Folkston D. Ray DIGSA 1,308 $19 $ 3,984,815 1,159 149 $ 540,047 Processing Center
Diamondback DIGSA 1,200 $40 $ 6,929,643 364 836 $ 5,844,896 Correctional Center
Delaney Hall CDF 700 — $ 3,913,524 860 0 —
Total — — — — — 2,614 $ 13,032,520
CDF = Contract detention facility; DIGSA = Dedicated intergovernmental service agreement; — = Not applicable Source: GAO analysis of ICE data. | GAO-27-108665
a At some facilities, ICE pays both a flat monthly fee that covers facility-wide expenses and a daily rate per bed that covers the care of each noncitizen, according to ICE officials. b For contracts at new facilities, ICE generally establishes a ramp-up plan where the monthly fee is gradually phased in to prevent ICE from paying for beds that the vendor is still standing up, according to ICE officials. c Average daily population data represent October 2025 through April 2026. Actual facility populations fluctuate daily and an increased number of fixed beds may have been utilized at various times during this period.
Note: We selected the five adult detention facilities with the largest number of fixed beds that ICE acquired and began operating during fiscal year 2025. We excluded two facilities, Camp East Montana and Midwest Regional Reception Center, from the sample because some fixed beds at those facilities may not have been available throughout the entire fiscal year. To estimate the amount that ICE paid per month for empty beds at these facilities, we (1) calculated the overall daily cost per fixed bed, accounting for both the flat monthly fee and daily rate if appliable; (2) calculated the average daily number of empty fixed beds by subtracting average daily population from the total number of fixed beds; (3) multiplied the daily cost per fixed bed by the average number of empty beds; and (4) multiplied the product by the average number of days per month.
In 2021, we recommended that ICE document and implement a strategic approach for using guaranteed minimums in detention contracts and agreements that supports strategic plans, goals, and priorities.36 In response to this recommendation, ICE reported in 2024 that it planned to
36GAO-21-149.
Page 24 GAO-27-108665 Immigration Detention
Page 30 of the original
phase out the use of guaranteed minimums and shift to a fixed monthly operating charge payment structure, where ICE pays a flat monthly fee for its anticipated usage level and has flexibility to renegotiate if it uses less space than anticipated. Although ICE’s use of fixed monthly charges has increased in subsequent years, this payment structure carries the same risk as guaranteed minimums because ICE is committing to paying for a fixed number of beds regardless of whether they are used, as exemplified in table 3 above. Additionally, as of June 2026, ICE had not provided examples of contracts or agreements that include the flexibility to renegotiate costs if it uses less space than anticipated.
Further, potential changes in policy, priorities, or resources may result in reduced populations in custody while ICE continues to pay for fixed beds at applicable facilities. Given the risk of ICE continuing to pay for empty beds at some facilities for years to come, we continue to maintain that implementing a strategic approach to using guaranteed payments would position ICE to secure better contract and agreement terms while more effectively using federal funds. We will continue to track ICE’s progress in doing so.
ICE Used High-Cost Facilities ICE utilized high-cost detention facilities at two military installations in on Military Installations fiscal years 2025 and 2026. While expanding detention space in response to presidential directives, ICE requested access to several installations for detention operations in February 2025.37 According to ICE officials, as of July 2026, ICE plans to maintain the existing detention operations at Camp East Montana (on U.S. Army Fort Bliss) and Naval Station Guantanamo Bay, but does not have plans to use any additional military installations.
Camp East Montana. In June 2026, we reported that the Army and ICE’s expedited time frames for opening Camp East Montana in August 2025 led to millions of dollars of waste.38 Specifically, the contract for operating the facility did not account for occupancy levels below the maximum, requiring ICE to pay for the full cost of meals and services for 5,000 people even when the facility houses a smaller population. ICE paid the
37Department of Homeland Security, Request for Department of Defense Assistance in Support of U.S. Immigration and Customs Enforcement Removal Operations (Feb. 12, 2025). ICE has not rescinded this request for assistance as of August 2026.
38The U.S. Army awarded and administered a contract for constructing and operating Camp East Montana on U.S. Army Fort Bliss in fiscal year 2025. The Army modified the contract in September 2025 to transfer contract administration responsibilities to ICE at the start of fiscal year 2026. GAO-26-108886.
Page 25 GAO-27-108665 Immigration Detention
Page 31 of the original
facility operator a flat monthly fee of over $38 million per month but did not consistently operate Camp East Montana at or near full capacity.
Further, agency data show that ICE obligated over $1 billion to Camp East Montana from October 2025 through June 2026, representing about 36 percent of the total $2.9 billion obligated to detention facilities during that period.39 In our June 2026 report, we recommended that ICE incorporate cost savings measures, such as tiered pricing for meals and other services, into the contracts at Camp East Montana and other facilities to account for fluctuations in population. DHS agreed with this recommendation and stated that it would modify the Camp East Montana contract to include tiered pricing. Accounting for fluctuations in population in detention facility contracts would improve cost efficiency at those facilities.
Guantanamo Bay. In January 2025, a presidential directive required DHS and DOD to expand the Migrant Operations Center, a preexisting DHS facility at Naval Station Guantanamo Bay, to full capacity to detain high-priority noncitizens unlawfully present in the U.S.40 DHS and DOD also repurposed a second Guantanamo Bay facility, Camp Six, for immigration detention. The combined capacity at both facilities was 400 beds as of August 2026.
39Specifically, ICE obligated about $598 million to the original contractor at Camp East Montana and later terminated that contract for convenience of the government. Contractors can have up to one year from the termination date of a contract to submit a settlement proposal. The government can either pay or negotiate this settlement amount. ICE awarded a new contract for operating this facility with an obligation of about $452 million, which is also subject to change when ICE and the contractor reach agreement on terms, specifications, and prices. According to ICE documentation approving the use of noncompetitive procedures for the new contract, the monthly cost for operating the facility is likely to be significantly higher than $38 million per month. Specifically, ICE estimated that monthly costs could exceed $68 million per month during the 7-month base period and potentially increase to over $90 million per month during optional extension periods up to 2 years.
40Expanding Migrant Operations Center at Naval Station Guantanamo Bay to Full Capacity, DCPD No. DCPD202500200 (Jan. 29, 2025). For years prior to this directive, ICE administered a contract at the Migrant Operations Center to temporarily house migrants interdicted at sea in the Caribbean region who need protection and do not consent to be repatriated. According to agency data, ICE spent approximately $1 million on the Migrant Operations Center contract in fiscal year 2023 and $4 million in fiscal year 2024. According to ICE officials, ICE uses surge flexibilities in its current contract to house detained noncitizens unlawfully present in the U.S. in addition to migrants interdicted at sea. However, no migrants interdicted at sea were housed at Guantanamo Bay from February 2025 through August 2026, according to DOD officials.
Page 26 GAO-27-108665 Immigration Detention
Page 32 of the original
We previously reported that Guantanamo Bay detention operations proceeded on a smaller scale than originally planned.41 However, use of this location has required high investment from ICE and DOD.42 As shown in table 4, both facilities had a combined average daily population of fewer than 30 detained noncitizens from October 2024 through June 18, 2026. Despite that population, ICE obligated approximately $43 million to expand and operate these facilities from October 2024 through June 2026, while DOD obligated approximately $68 million from October 2024 through May 2026. These costs include DOD’s military flights transporting detained noncitizens to and from Guantanamo Bay, but do not include ICE’s chartered flights.43 See appendix IV for additional information on DOD’s costs for supporting ICE detention.
41GAO-26-108663.
42DOD bore most costs associated with expanding and operating Camp Six in fiscal year 2025, while ICE continued administering and funding the contract at the Migrant Operations Center, according to officials at both agencies. According to agency documentation, the Department of Homeland Security agreed to reimburse DOD for support of immigration detention provided from the start of fiscal year 2026 through the end of fiscal year 2035.
43According to officials, ICE aggregates these costs along with other flights performed by its air charter contractor. DOD’s Inspector General and the U.S. Department of State Office of the Inspector General jointly reported that DHS reported spending an estimated $12 million on chartered flights to and from Guantanamo Bay in fiscal year 2025. DOD spent approximately $22 million on military flights that year, with the first flight costing over $22,000 per detained noncitizen. Department of Defense Inspector General and U.S. Department of State Office of the Inspector General, Lead Inspector General Report to the United States Congress: Operation Southern Guard, July 1, 2025 – December 31, 2025.
Page 27 GAO-27-108665 Immigration Detention
Page 33 of the original
Table 4: Detained Populations and Obligations at Guantanamo Bay, Fiscal Years 2025 and 2026
U.S. Immigration and Department of Average daily Maximum daily Customs Enforcement Defense (DOD) Fiscal year population populationa (ICE) obligationsb c Total obligations obligations
2025 28 noncitizens 178 noncitizens $ 25,135,498 $ 60,645,278 $ 85,780,776
2026 (partial) 16 noncitizens 115 noncitizens $ 17,582,997 $ 7,449,169 $ 25,032,166
Total — — $ 42,718,495 $ 68,094,447 $ 110,812,942
— = Not applicable Source: GAO analysis of U.S. Immigration and Customs Enforcement (ICE) and Department of Defense (DOD) data. | GAO-27-108665
a Average and maximum daily population data represent both Guantanamo Bay facilities throughout fiscal year 2025. For fiscal year 2026, these data represent the population from October 1, 2025, through June 18, 2026. b ICE data represent obligations through June 30, 2026. These data do not include obligations related to transporting detained noncitizens to and from Guantanamo Bay. ICE aggregates these costs along with other flights performed by its air charter contractor. c DOD data represent obligations through May 31, 2026. According to agency documentation, the Department of Homeland Security agreed to reimburse DOD for its support of immigration detention provided from the start of fiscal year 2026 through the end of fiscal year 2035.
Guantanamo Bay involves substantially higher costs than facilities where ICE alone is paying for a similar number of beds. For example, in fiscal year 2025, ICE obligated approximately (1) $40 million at Florence Service Processing Center, with 392 fixed beds and an average daily population of 386 detained noncitizens and (2) $41 million at Buffalo Service Processing Center, with 400 fixed beds, 650 total beds, and an average daily population of 626 detained noncitizens. In the same year, ICE and DOD obligated approximately $86 million for 400 beds at Guantanamo Bay with an average daily population of 28 detained noncitizens.
Despite the high costs of detention at Guantanamo Bay, ICE has not restricted the use of Camp Six to detain high-threat noncitizens as originally planned. Specifically, the memorandum of understanding DOD and DHS signed in March 2025 established that ICE would use Camp Six to house high-threat noncitizens with a nexus to transnational criminal organizations or criminal drug activity.44 According to agency documentation, ICE designates noncitizen threat levels based on
44Memorandum of Understanding Between the U.S. Department of Homeland Security (DHS) and the U.S. Department of Defense (DOD) for DOD Support at Naval Station Guantanamo Bay (NSGB) to U.S. Immigration and Customs Enforcement (ICE) for DHS/ICE Detention of Illegal Aliens Subject to Final Orders of Removal, March 7, 2025. According to agency documentation and ICE and DOD officials, the agencies extended this agreement with the same conditions through fiscal year 2026.
Page 28 GAO-27-108665 Immigration Detention
Page 34 of the original
criminality and classifies noncitizens without a criminal conviction as having “no threat level.” However, ICE placed multiple noncitizens who had no criminal convictions or pending charges at Camp Six, as shown in table 5.
Table 5: Criminality of Detained Population at Guantanamo Bay Camp Six, August 2025 – April 2026
Number of Detained Noncitizens
With Criminal Conviction or No Criminal Conviction Pending Charges or Pending Charges Total
August 2025 11 6 17
September 2025 12 5 17
December 2025 1 1 2
February 2026 4 12 16
April 2026 3 11 14
Source: GAO analysis of ICE data. | GAO-27-108665
Note: These data represent snapshots in time per each listed month and are sourced from ICE’s public detention statistics. Missing months represent periods when ICE did not update those statistics—which coincided with lapses in federal funding during which some ICE staff were furloughed—or periods when Camp Six did not appear in the data because there were zero noncitizens detained there at the time ICE pulled the data. For example, officials said that neither Guantanamo Bay facility housed detained noncitizens from approximately October through mid- December 2025 due to hurricane evacuation and ensuing damage. ICE most recently updated its public statistics in July 2026, but Camp Six did not appear in the data, likely because it housed zero noncitizens at that time.
ICE officials stated that costs did not factor into the decision to use Guantanamo Bay and that conserving costs is not a goal for operations there. According to ICE officials, the agency plans to continue using Guantanamo Bay based on direction from senior leadership and the White House.
Newly Purchased Detention From the initial property acquisitions to the planned renovations and Facilities Are Likely to Entail operations, ICE’s approach to purchasing warehouses and existing High Costs detention facilities is likely to entail high costs. Although the scope and timing of this approach remain undetermined, initial obligations and preliminary cost projections indicate that ICE’s approach may have significant long-term budgetary impacts. Specifically:
• Warehouse acquisitions. Our analysis of ICE documentation and public records showed that ICE potentially overpaid for many of the warehouses it purchased. Although tax assessment data is not always a reliable indicator of fair market value, we found that ICE paid at least
Page 29 GAO-27-108665 Immigration Detention
Page 35 of the original
50 percent above the state or local government’s assessment of taxable value for nine of the 11 warehouses.
Moreover, given ICE’s plans to sell seven of the warehouses—six for which it paid at least double the assessed value—there is risk that these sales could result in financial losses to the federal government. Additional sunk costs include approximately $7.7 million for related due diligence activities for the purchase of those seven facilities, as well as $12.8 million for utilities, security, and other services as of August 2026. See appendix V for additional information on public records of assessed value and prior sales for the 11 warehouse properties.
• Warehouse renovation and operating costs. Based on obligations to date and preliminary cost estimates, renovating and operating the four warehouses ICE plans to retain may require significant investment from ICE. For example, ICE obligated $313 million for renovation and ramp-up activities at Surprise, Arizona and $113 million on the Williamsport, Maryland warehouse renovation contract.
Further, ICE’s preliminary estimates indicate that the agency believes three of the four warehouses it plans to retain could each have annual operating costs that are significantly higher than those of most ICE facilities in fiscal year 2025, including the five ICE-owned service processing centers.45
Although ICE originally planned to phase out existing facilities after renovating warehouses, officials said they are now unlikely to pursue that plan. The four warehouses currently planned would hold a maximum of 6,000 beds, which will require ICE to retain many of its existing facilities to house the current fiscal year’s average daily population of 67,180 detained noncitizens as of July 30, 2026. If ICE proceeds with this approach, it may result in high acquisition and operating costs without securing significant savings, which could have long-term impacts on ICE’s budget and operations.
In addition, ICE’s purchase of four existing detention facilities between July and August 2026 for a combined total of about $2.2 billion indicates this approach will also entail high costs. According to planning documents, ICE was considering purchasing seven additional facilities it currently uses in states such as Colorado, New Jersey, and Washington as of July 2026. Officials noted that while they do not expect this effort to
45ICE-owned facilities had capacity ranging from 650 to 1,175 beds in June 2026 compared to ICE’s goal of 1,500 beds at each warehouse.
Page 30 GAO-27-108665 Immigration Detention
Page 36 of the original
result in cost savings, it will help ICE fulfill its mission in locations where state governments may resist expanded detention efforts. Although ICE planning documents indicate that ICE may expand bedspace in some of the purchased facilities, doing so may require significant investment. For example, ICE’s preliminary estimates for the newly purchased California City facility indicate that the agency believes annual operating costs could be significantly higher than comparable facilities after expanding capacity to 5,000 beds.46
ICE Employs Various Cost Management and Oversight Processes, but Did Not Fully Assess Cost Effectiveness Amidst Facility Expansion ICE Conducts Various ICE employs various processes to manage and oversee facility costs at Levels of Cost Oversight, several stages and agency levels, but some activities have been affected by the rapid expansion of new detention facilities. We identified three key but Facility Expansion Has processes performed by field and headquarters officials that are intended Affected Some Processes to (1) inform decisions for additional bedspace; (2) validate facility invoices; and (3) track and monitor facility costs:
New bedspace proposals. ICE’s standard process for acquiring additional detention bedspace typically begins with the development of a proposal at the field office level, known as a “white paper.” However, according to officials, this process was not the only mechanism used for preliminary decision-making about new or expanded facilities since January 2025 and did not apply to the warehouse purchases in 2026. As we reported in January 2021, the white paper process is designed to be “bottom up” to identify a field office’s detention needs and evaluate costs and other tradeoffs.47 The white paper template also directs field officials
46ICE officials also estimate approximately $100 million for renovation costs at this facility in addition to the $730 million purchase price. According to ICE officials, these cost projections are intended to serve as rough estimates for internal purposes. Additional information regarding ICE cost estimates for new facilities is discussed later in this report.
47GAO-21-149.
Page 31 GAO-27-108665 Immigration Detention
Page 37 of the original
to include information on transportation requirements, medical care facilities, and key local stakeholders (such as mayors or sheriffs) that indicated their support for the proposal, among other requirements. Field management is to review and approve the white papers before providing them to ERO for final acquisition decisions. We selected a sample of 12 large or high-cost detention acquisitions that ICE made in fiscal year 2025 and found that ICE developed white papers for 11 of them.48
Although ICE officials did not identify a specific policy requirement for field offices to complete white papers, they reported that developing white papers remains a standard practice to document new facility proposals and provide preliminary cost estimates based on comparable facilities in the area. However, officials from all four field offices we spoke to told us that white papers were not always the key driver for decisions regarding expansion of detention space since January 2025, given the significant surge in demand for new facilities nationwide. For example, one official noted that several white papers they have submitted since 2025 were developed after a facility acquisition was already initiated by headquarters. According to ERO officials, DHS and ICE leadership also led decisions regarding expanded detention space in many new facilities in 2025, such as those operated by BOP, Guantanamo Bay, and Camp East Montana.
In addition, none of the warehouse acquisitions were subject to the white paper process, which DHS initiated and the ICE Office of Asset and Facilities Management managed centrally. Given the number of legal challenges filed by state and local officials in several of the jurisdictions where ICE purchased the new warehouses, obtaining stakeholder input about these facilities in advance (which we recommended in 2021) could have helped ensure local buy-in and manage risk.49 Specifically, DHS and ICE leadership may have been able to take steps to minimize legal or other risks before completing warehouse acquisitions in certain
48Among these facilities, the Dilley Detention Center was the only facility lacking a white paper. We did not include Delaney Hall in our analysis of white papers because this facility was reopened in 2025 and, according to ICE officials, was awarded as part of a broader facility contract solicitation and not subject to the white paper process.
49GAO-21-149. In January 2021, we recommended that ERO consistently use a process that includes input from relevant stakeholders and documentation of the basis for decisions made before entering into contracts or agreements for new or expanded detention space. In response, ICE reported taking action in 2022 to provide field offices with additional guidance regarding the bedspace proposal process; however, as of June 2026, ICE had not provided documentation confirming it is using the new process in practice.
Page 32 GAO-27-108665 Immigration Detention
Page 38 of the original
jurisdictions, which now has significant cost implications as ICE has initiated plans to sell over half of the existing warehouses.
Facility invoice validations. CORs perform routine oversight and Contracting Officer’s Representative (COR) validation of all facility invoices; however, the four CORs we spoke to A COR is appointed by a contracting officer reported that the increased number of detention facilities since January and provides technical direction, clarification, 2025 has strained their ability to dedicate adequate time and attention to and guidance with respect to the contract or agreement terms. this role. In addition to the review and validation of monthly facility The COR is the technical liaison between the invoices, CORs have a range of other roles and responsibilities, such as detention facility operator and the contracting (1) visiting detention facilities to ensure that vendors comply with the officer and is responsible for monitoring the performance of the facility operator according contract or agreement, (2) monitoring the status of funds available for to the contract or agreement each facility, and (3) supporting new hire processing at the facilities. Source: GAO analysis of ICE information. | GAO-27-108665 According to all four of the CORs we spoke to, the expanded number of detention facilities has made it challenging to carry out their assigned duties, including providing rigorous oversight of facility cost invoices. See figure 7 for additional information on the facility invoice validation process.
Figure 7: Key Steps in the U.S. Immigration and Customs Enforcement (ICE) Detention Facility Invoice Validation Process
Page 33 GAO-27-108665 Immigration Detention
Page 39 of the original
At the end of December 2025, ICE reported there were a total of 32 CORs who conducted detention facility oversight across ERO’s 25 field offices, and 55 vacant positions. As discussed above, the number of ICE detention facilities roughly doubled between January 2025 and June 2026, which significantly increased the COR workload. For example, one COR reported that their oversight responsibilities increased from 10 to 31 facilities from January to December 2025. Moreover, some of these CORs are the only ones serving this role in their designated field offices and reported they have limited backup support.
ICE headquarters officials acknowledged that the need for additional CORs was a longstanding issue and stated that, as of May 2026, ICE had an open vacancy announcement to hire additional COR positions in fiscal year 2026. In August 2026, officials reported that the hiring actions remained underway to address the 55 vacancies across ICE field offices. However, ICE did not provide any supporting documentation to verify the number of positions available or how many were filled to date. According to ICE officials, the agency generally focused its recent hiring efforts on enforcement positions, stalling COR-related activities, in part, due to the funding lapse and partial ICE shutdown in 2026. According to officials, hiring CORs can also be challenging due to the requirements for prior contract oversight experience. Although hiring additional CORs will help alleviate some of the existing staffing and workload challenges cited, it will likely remain difficult to determine precisely what near- and longer-term COR resources will be needed until ICE determines the scope and timeframes for further warehouse development and other planned expansion of the existing detention facility structure.
ICE headquarters officials noted that ERO has implemented an initiative to assist CORs with reconciling detention invoices. The initiative, referred to as the Robotic Process Automation process, provides an automated validation of vendor submission details, such as detention days, bed rates, mileage reimbursements, and detainees at the facility per ICE records. It also provides a summary report to flag any discrepancies for the CORs attention. According to officials, this process reduces the time required for CORs to review vendor invoice submissions and, as of August 2026, was used for 120 facilities. Each of the four CORs we spoke to were familiar with this new initiative, and three specifically noted it was helpful and saved time by pre-populating contract information and detainee information for the larger facilities.
Monitoring of facility costs and budget execution. ICE headquarters offices conduct routine oversight and monitoring of facility detention costs
Page 34 GAO-27-108665 Immigration Detention
Page 40 of the original
and budget execution. Specifically, the Operations Support Division conducts regular tracking and reporting of monthly facility obligations, budget execution, and related metrics to support financial oversight of detention services in coordination with the Office of Budget and Program Performance. For cost accounting and reporting purposes, ICE manages annual appropriations and OBBBA funds separately, and allocates funds from these accounts using individual line items for each facility.
Oversight and tracking efforts also include monitoring the timeliness of ICE’s reimbursements to facility vendors. ICE data show that the agency paid over $500,000 in interest on late invoices for enforcement and removal activities from October 2024 through December 2025. According to Operations Support Division officials, ICE has faced significant delays in this area due, in part, to multiple government shutdowns and a prior DHS review policy, which affected the timely obligation of facility funding. See appendix VI for more information.
ICE Has Not Assessed Since ICE initiated its efforts to rapidly expand detention capacity in early Cost Effectiveness Amidst 2025, it has entered into multiple acquisition and contracting decisions that raise concerns about cost effectiveness and are not aligned with Facility Expansion DHS acquisition management practices.50 For example, the nine BOP facilities ICE used in 2026 have the highest median bed rate of any facility type, and both facilities on military installations resulted from expedited processes and have entailed high costs and lower than expected usage. The warehouse initiative, in particular, also represents a major investment that was implemented rapidly without a clear accounting of estimated life-cycle costs to inform decision making. As discussed above, ICE estimated total fiscal year 2026 obligations of $38 billion to implement the warehouse detention initiative. However, ICE did not provide any evidence documenting the underlying costs or analyses used to develop these estimates when requested. Further, ICE did not provide any type of cost effectiveness assessment that it may have used to inform the property purchase and selling decisions, amidst other potential alternatives.
Similarly, ICE officials told us they had only developed “rough cost estimates” for the contracted detention facilities they plan to purchase and potentially expand. Although ICE stated that these rough estimates are being used to inform internal decision-making, it is unclear how they were
50DHS’s Acquisition Management Directive establishes a framework for managing large investments, including capital assets, infrastructure, and mission-enabling services. See DHS Directive 102-01, Acquisition Management (Nov. 17, 2025).
Page 35 GAO-27-108665 Immigration Detention
Page 41 of the original
developed and what underlying cost assumptions were used. For example, ICE estimated operating costs at the newly acquired California City facility would be substantially higher than the monthly operating cost of the Camp East Montana facility with similar capacity (at $38 million per month). However, ICE provided no information on the assumptions underlying this estimate.
ICE’s detention facility investments were not managed in accordance with key principles identified in DHS’s acquisition management directive. This directive emphasizes the importance of assessing planned investments, such as developing life-cycle cost estimates and analyzing alternatives or tradeoffs before committing significant resources.51 In addition, according to OMB guidance, a project is cost-effective if, based on life-cycle cost analysis of competing alternatives, it is determined to have the lowest costs for a given amount of benefits.52 The guidance notes that a cost-effectiveness analysis is appropriate even if it is unnecessary or impractical to consider the dollar value of benefits. Analyzing alternatives can be done by examining different project scales, methods of provision, and varying degrees of government involvement. For example, in analyzing a decision to acquire a capital asset, the analysis should generally consider potential conversions of existing government property, or leasing, in addition to a direct purchase.
According to ICE ERO officials, administration and DHS leadership were largely responsible for certain detention expansion decisions, such as using military facilities and acquiring warehouses. Officials in the DHS Office of the Chief Procurement Officer and Office of the Chief Readiness Support Officer also noted that certain acquisition management and oversight activities for investments of this size were not conducted. For example, these officials stated that they were not involved in discussions within the department about whether to plan and manage ICE’s initiatives—such as the warehouse, contracted detention facility purchases, or high-dollar detention service contracts—as major
51Life-cycle costs include the overall estimated cost for a particular project over the time period corresponding to the life of the project, including direct and indirect initial costs plus any periodic or continuing costs of operation and maintenance. We have previously reported that operations and maintenance costs for federal buildings can be significantly higher over time than all other costs, including construction, and typically account for 60 to 80 percent of building life cycle costs. See, for example, GAO, Federal Buildings: More Consideration of Operations and Maintenance Costs Could Better Inform the Design Excellence Program, GAO-18-420 (Washington, D.C.: May 2018).
52Office of Management and Budget, Circular No. A-94, Guidelines and Discount Rates for Benefit-Cost Analysis of Federal Programs, Revised, Nov. 9, 2023.
Page 36 GAO-27-108665 Immigration Detention
Page 42 of the original
acquisition programs. This would have entailed additional planning and analysis including assessing alternatives, documenting major decisions, and developing life-cycle cost estimates. According to these officials, under the current acquisition management directive, the DHS Undersecretary for Management can also require components to follow certain acquisition program pathways at any point.
Given the significant costs and long-term budgetary impacts associated with all of the large detention facilities, it is important that ICE develop robust life-cycle cost estimates to inform any future investment decisions before proceeding with further acquisitions. Without life-cycle cost estimates, ICE is making decisions about which warehouses to sell or renovate and which contracted detention facilities to purchase without complete information, including which efforts may be more cost effective. For example, ICE’s decision to sell seven of the 11 recently purchased warehouses entails immediate sunk costs and demonstrates the potential for significant waste, highlighting the importance of properly evaluating the costs, benefits, and risks of various alternatives before making acquisition decisions. ICE’s planned initiative to acquire additional contract-detention facilities may also present risk if the need for detention space is reduced in the future, as this could result in taxpayer funds being spent on unused beds. Given that ICE plans to make continued investments toward these expansion efforts, their strategic importance to the administration, and the financial risks ICE has already experienced with its efforts to date, it is critical that ICE manage future detention investments in coordination with appropriate DHS Undersecretary of Management offices. Further, managing future detention investments in accordance with established acquisition practices would better inform decision making and avoid the risk of further inefficiency and wasted taxpayer dollars.
As ICE continues to spend the unprecedented detention funding provided Conclusions by OBBBA and the Secure America Act, it is imperative that the agency uses these taxpayer dollars in a cost-effective manner. The warehouse initiative is an example of a major investment that was implemented rapidly and will likely result in significant waste. Given the need to adequately manage these funds until fiscal year 2029, spending plans remain a critical tool to plan and monitor ICE obligations and ensure adequate funding remains available to support ongoing detention operations. However, ICE did not update its OBBBA spending plan for detention funding throughout fiscal year 2026 to reflect the significantly changing conditions regarding planned facility investments. By ensuring that OBBBA spending plans are updated in accordance with ICE’s own
Page 37 GAO-27-108665 Immigration Detention
Page 43 of the original
internal guidance and based on realistic assumptions, ICE will be able to provide more accurate information to DHS leadership, OMB, and Congress, and will be better positioned to project longer-term budget needs when OBBBA funding is no longer available.
Although ICE developed preliminary high-level estimates for some of its detention investments, it did not provide evidence for any of the underlying cost assumptions or any analyses conducted to assess the cost effectiveness of these investment decisions. According to OMB and DHS Acquisition guidance, such analyses would consist of developing life-cycle cost estimates for each of these facilities to compare among potential alternatives and inform decision making. Lacking these life-cycle cost estimates, ICE will likely continue to make investment decisions with limited information and risk overpaying for these acquisitions. Now that ICE has awarded renovation and operating contracts for two of the warehouse facilities, it has an opportunity to develop more comprehensive life-cycle cost estimates to evaluate the cost effectiveness of these efforts and inform any further warehouse development plans. Similarly, ICE is making decisions about which warehouses to sell or renovate and which additional contracted detention facilities to purchase without complete information. As ICE proceeds to execute spending on new or renovated detention facilities, these investments can be more fully informed by a cost effectiveness analysis to help ensure that any perceived benefits justify the anticipated costs. Such efforts will be critical to ensure that taxpayer dollars are spent wisely.
We are making the following two recommendations to ICE: Recommendations for Executive Action The Director of ICE should ensure that agency spending plans for ICE detention funds, including those received through the reconciliation process, are updated in a timely manner in accordance with ICE policy and include all required elements. (Recommendation 1)
The Director of ICE, in coordination with the DHS Undersecretary for Management, should develop life-cycle cost estimates and evaluate alternatives to inform any significant future detention facility investments. (Recommendation 2)
We provided a draft of this report to DHS, the Department of Justice, and Agency Comments the Department of Defense for review and comment. DOD and the and Our Evaluation Department of Justice did not provide comments. In its written comments, reproduced in appendix VII, DHS agreed with the two recommendations and requested that we close one as implemented based on activities ICE
Page 38 GAO-27-108665 Immigration Detention
Page 44 of the original
had completed—and that we considered—during our review. We maintain both our recommendations remain warranted, as discussed below. DHS also provided technical comments, which we incorporated as appropriate.
Regarding our first recommendation, DHS stated that applicable spending plans were developed, approved, and updated in fiscal year 2026 in accordance with ICE policy guidance. However, as discussed in the report, ICE’s OBBBA spending plan for detention funding was not updated in a timely manner to reflect material changes, such as the decision to significantly reduce the scope of the warehouse detention initiative. Specifically, the spending plan information provided to us in July 2026 still maintained an estimate of over $38 billion in planned obligations for fiscal year 2026 although this was no longer a realistic assumption and did not reflect current conditions (ICE reported total OBBBA detention funding obligations of about $10 billion at the end of fiscal year 2026). In addition, the plan provided did not include any supporting information, such as the purpose and schedule for planned obligations. To fully address this recommendation, ICE needs to provide evidence that the fiscal year 2027 spend plan for detention funding includes more realistic budget execution assumptions, as well as documentation regarding the underlying data and supporting details provided by applicable program offices.
With respect to recommendation 2, DHS stated that applicable ICE offices will coordinate with the DHS Management Directorate to develop a standardized process to inform significant future detention facility investments, which will include development of life-cycle cost estimates and evaluation of reasonable alternatives. As part of this effort, ICE is to develop a tracking document that will support fiscal oversight and provide evidence for investment decisions. We will monitor these efforts to address our recommendation.
We are sending copies of this report to the appropriate congressional committees, the Secretary of Homeland Security, and other interested parties. In addition, the report is available at no charge on the GAO website at https://www.gao.gov.
Page 39 GAO-27-108665 Immigration Detention
Page 45 of the original
If you or your staff have any questions about this report, please contact me at MacLeodH@gao.gov. Contact points for our Offices of Congressional Relations and Media Relations may be found on the last page of this report. GAO staff who made key contributions to this report are listed in appendix VIII.
Heather MacLeod Director, Homeland Security and Justice
Page 40 GAO-27-108665 Immigration Detention
Page 46 of the original
List of Requesters
The Honorable Jack Reed Ranking Member Committee on Armed Services United States Senate
The Honorable Gary C. Peters Ranking Member Committee on Homeland Security and Governmental Affairs United States Senate
The Honorable Richard J. Durbin Ranking Member Committee on the Judiciary United States Senate
The Honorable Bennie G. Thompson Ranking Member Committee on Homeland Security House of Representatives
Page 41 GAO-27-108665 Immigration Detention
Page 47 of the original
Appendix I: ObjAeppecndixt Ii: Ovbjeesctives, S,c Sope and cope and Methodology Methodology
This report examines (1) the extent to which U.S. Immigration and Customs Enforcement (ICE) has planned to use available funds to expand detention capacity, (2) the costs of immigration detention facilities over time and by facility type, and (3) the extent to which ICE has developed processes and procedures for managing and overseeing facility costs.
ICE’s Planned Use of Available To examine the extent to which ICE has planned to use available funds, Funds we analyzed ICE Enforcement and Removal Operations (ERO) program execution reports and other information ICE provided to identify detention funding sources and amounts from October 2022 through September 2026. We reviewed two appropriations acts passed through the reconciliation process and enacted in 2025 and 2026 respectively, that provide funding to ICE to understand the amount available for operating and expanding detention space: Public Law 119-21, commonly known as the One Big Beautiful Bill Act (OBBBA), and the Secure America Act.1
Additionally, we evaluated ICE’s fiscal year 2025 and 2026 spending plans for OBBBA funds to understand the intended uses of those funds and the extent to which ICE adhered to internal guidance for developing spending plans. Specifically, we assessed OBBBA spending plans against ICE’s internal guidance, which states that spending plans should be updated regularly.2
Further, we reviewed documentation related to the Detention Reengineering Initiative, ICE’s plan to purchase and renovate warehouses into detention facilities and purchase existing detention facilities. Additionally, we visited the warehouse ICE purchased in Social Circle, Georgia, as part of our field office interviews—described in further detail below—to observe the site and interview officials responsible for overseeing it. Finally, we interviewed ICE officials to understand funds available for detention facilities, plans for using those funds, and processes for developing those plans. These included officials from ERO
1An Act to provide for reconciliation pursuant to title II of H. Con. Res. 14, Pub. L. No. 119- 21, title IX, subtitle A, § 90003, 139 Stat. 72, 358; Pub. L. No. 119-98, title II, § 202, 140 Stat. 837, 839.
2U.S. Immigration and Customs Enforcement, Office of the Chief Financial Officer and Office of Budget and Program Performance, FY 2025 Spend Plan Guidance (July 2024). As of May 2026, ICE was in the process of updating this guidance for fiscal year 2027; however, the draft document ICE provided to us maintains the same criteria for required updates as existed in the prior version.
Page 42 GAO-27-108665 Immigration Detention
Page 48 of the original
Appendix I: Objectives, Scope and Methodology
financial and program offices and the Office of Budget and Program Performance.
Costs of Immigration Detention To describe the costs of immigration detention facilities, we collected data Facilities and other information from ICE and the Department of Defense (DOD) and documentation from the Federal Emergency Management Agency on obligations and other planned costs associated with those facilities. We determined the data we used to be sufficiently reliable for describing detention facility costs.
Specifically, we analyzed ICE data from October 2022 through 2026, with the end dates varying based on when ICE provided the data. We selected this period to compare the obligations for detention space in 2025 and 2026—when expansion efforts began—to obligations for detention space in the prior 2 fiscal years. Specifically, we analyzed data on the following topics:
• The number and type of facilities as of June 2026 and average daily population overall and by certain facilities from October 2022 through June 2026. ICE maintains these data in the ICE Integrated Decision Support system, used for tracking information on individuals in custody, as well as other enforcement information.
• Annual obligations from October 2022 through June 2026 for detention facilities and through July 2026 for ground transportation of detained noncitizens. ICE maintains these data in its financial system, the Federal Financial Management System.
• Daily bed rates, monthly operating charges, and fixed beds by facility from October 2022 through April 2026. ICE maintains files on this information.
• Interest penalties paid on invoices related to ERO activities from October 2022 through December 2025.
We analyzed ICE’s overall obligations for detention facilities and compared annual costs and bed rates by facility ownership type. For facilities that used tiered pricing, which have multiple bed rates at different levels of utilization, we calculated a bed rate based on 100 percent utilization of all beds and leveraged ICE’s April 2026 list of authorized facilities to address data issues with the variables concerning pricing and number of beds at a small number of facilities. We also identified the number of facilities where ICE committed to make guaranteed payments on a fixed number of beds from October 2022 through April 2026 and the average daily population at those facilities throughout fiscal year 2026 (as
Page 43 GAO-27-108665 Immigration Detention
Page 49 of the original
Appendix I: Objectives, Scope and Methodology
of April) to understand the extent to which ICE is utilizing fixed beds on average during that year.
Additionally, we selected five adult detention facilities with a large number of fixed beds that ICE acquired after fiscal year 2024. We took the following steps to estimate the amount that ICE paid per month for empty beds at these facilities.
1. We calculated the overall daily cost per fixed bed by (1) dividing the flat monthly fee by the number of fixed beds, (2) dividing that result by 30.42, the average number of days per month, and (3) adding the daily bed rate if applicable.
2. We calculated the average daily number of empty fixed beds by subtracting average daily population from the total number of fixed beds.
3. We estimated the monthly cost for empty beds by (1) multiplying the daily cost per fixed bed by the average number of empty beds and (2) multiplying that product by 30.42 (the average number of days per month).
Further, we collected information on ICE’s reported costs for purchasing 11 warehouses as part of the Detention Reengineering Initiative and related due diligence, security, and utility costs. We searched public records from county and city tax assessors to identify the assessed value of the 11 warehouse properties, and, where possible, previous sale prices from recent years. We compared this information to the prices ICE paid for the warehouses to determine how much ICE paid relative to those assessed values. Further, we reviewed public records on ICE’s purchase of four existing detention facilities to describe the costs of these purchases.
In addition to analyzing ICE’s detention costs, we analyzed DOD data on the costs of its support of immigration detention from October 2024 through May 2026. We selected this period for our analyses because DOD initiated support efforts to address January 2025 presidential directives and subsequent requests from the Department of Homeland Security (DHS). We used these data to present aggregate totals per fiscal year of DOD’s obligations for each activity. Specifically, we analyzed DOD’s obligations for the following activities:
• Supporting three immigration detention facilities: Naval Station Guantanamo Bay, Camp East Montana on U.S. Army Fort Bliss, and
Page 44 GAO-27-108665 Immigration Detention
Page 50 of the original
Appendix I: Objectives, Scope and Methodology
a facility previously used by U.S. Customs and Border Protection. Specifically, we used the Homeland Border Security Initiatives Execution Reports that DOD provides to Congress using its Advancing Analytics system (now called the War Data Platform). This system collects and aggregates data via a direct interface with military departments’ financial management systems.
• National Guard support activities performed at ICE detention facilities and other locations. We utilized data from the Army’s financial system of record, General Fund Enterprise Business System.
In order to assess the reliability of the ICE and DOD data used in our analyses, we (1) interviewed and obtained written responses from officials at both agencies about their management of the data; (2) reviewed relevant documentation; and (3) conducted electronic tests to identify missing, duplicate, and erroneous data. We determined the data were sufficiently reliable for describing ICE detention costs from October 2022 through various points in 2026 and DOD’s support of immigration detention from October 2024 through May 2026.
We also interviewed ICE officials to gain their perspectives on trends and variances in ICE facility bed rates. Finally, we reviewed documents and interviewed officials from the Federal Emergency Management Agency regarding the costs associated with a grant awarded to fund two immigration detention facilities operated by the state of Florida.