Government Accountability Office: Federal Data Centers: Congress Has an Opportunity to Improve Agencies' Acquisition and Operations

The text Dorworth News extracted from the kept copy

Download the original (PDF, 726 KB)

Fingerprint
9b2ad4ddfbd77fde46a879b33cf10e00d1da4eb42bc7eb5d7bce68e54c2f6748SHA-256 of the kept copy exactly as received.
Original
https://www.gao.gov/assets/gao-27-108971.pdf
The text
518 paragraphs, read from the kept copy, kept . The words are the document’s own; the layout is the site’s. Its words are read line by line across each page; columns, tables and pictures are not kept here.
1

United States Government Accountability Office Report to Congressional Committees

2

November 2026 FEDERAL DATA CENTERS

3

Congress Has an Opportunity to Improve Agencies’ Acquisition and Operations

4

GAO-27-108971

Page 2 of the original

5

FEDERAL DATA CENTERS

6

Highlights Congress Has an Opportunity to Improve Agencies' Acquisition and Operations GAO-27-108971 November 2026

7

A report to congressional committees

8

For more information, contact: Carol Harris at harriscc@gao.gov.

9

What GAO Found Why GAO Did This Study Of the 24 Chief Financial Officers Act agencies, 21 reported having data centers. Federal agencies use data centers for Those 21 agencies varied in incorporating the Office of Management and their mission-critical data and Budget’s (OMB) five acquisition and operational requirements into the operations. In December 2023, management and planning of their data centers. As of August 2026, none of the Congress passed the Federal Data agencies had fully addressed all five requirements. For example, nine agencies Center Enhancement Act of 2023 to ensure high standards of cybersecurity, reported using automated tools to monitor data center operations but the resiliency, and availability for federal documentation they provided did not always reflect this. In addition, for the five data centers. In response, in January agencies with new data centers, all of them partially addressed the requirement 2025, OMB established five minimum to incorporate energy and water usage into decision-making. Furthermore, many requirements for acquiring and agencies reported meeting mission availability requirements but did not operating federal data centers. demonstrate that they had a process for managing risks to determine the Agencies were to have satisfied these maximum tolerable duration and frequency of downtime for their data centers. requirements by January 14, 2026, for agency-operated data centers, with Extent to Which Federal Agencies Addressed OMB’s Acquisition and Operational potentially later dates for contractor- Requirements for Data Centers, as of August 2026 operated data centers. Requirement Fully addressed Partially addressed Not addressed Make key data center decisions The act includes a provision for GAO to at the agency level 10 11 0 annually review and verify the Monitor data center operations compliance of the 24 Chief Financial using automated tools 10 9 2 Officers Act agencies with OMB’s Incorporate energy and water requirements for new and existing data a centers. In this third and final review, usage into decision-making 0 5 0 GAO’s objective was to determine the Meet mission availability requirements 2 19 0 extent to which federal agencies have incorporated OMB’s acquisition and Meet information security and operational requirements for data physical security requirements 4 17 0 centers. Legend: Fully addressed = The agency fully addressed all of the requirement’s evaluation criteria. GAO analyzed 21 agencies’ data center Partially addressed = The agency fully or partially addressed some, but not all, of the requirement’s evaluation criteria. Not addressed = the agency did not address any of the requirement’s evaluation documentation, including policies, criteria. procedures, and risk management and security plans. GAO then assessed the Source: GAO analysis of agency documentation. | GAO-27-108971 results of the analysis against the five a The requirement was not applicable for 16 agencies because they reported having no new data OMB requirements. GAO also centers and OMB did not require agencies to apply the requirement to existing data centers. interviewed relevant agency officials. GAO is not making recommendations to the agencies because, in accordance with the Federal Data Center Enhancement Act (FDCEA) of 2023, the OMB What GAO Recommends requirements expired on September 30, 2026. Since the law was enacted in Congress should consider reauthorizing 2023, the IT landscape has changed. Advances in artificial intelligence the FDCEA or replacing it with a new capabilities and its growing use among agencies have further increased demand law reflecting updated priorities and for high-performance computing provided by data centers. Congress has OMB’s acquisition and operational introduced various legislative proposals for data centers that are intended to, requirements for agencies’ data among other things, address data center energy use reporting. Although these centers. apply more broadly to data centers nationwide, they may also impact federal data centers. If Congress takes legislative action to reauthorize or replace the FDCEA, it has the opportunity to direct OMB to update requirements for agencies to continue their efforts to enhance the cybersecurity, resiliency, and availability of data centers.

10

United States Government Accountability Office

Page 3 of the original

11

Contents

12

Letter 1

13

Background 3 Federal Agencies Varied in Incorporating OMB’s Acquisition and Operational Requirements for Their Data Centers 14 Conclusions 21 Matter for Congressional Consideration 22 Agency Comments 22

14

Appendix I Objective, Scope, and Methodology 24

15

Appendix II Detailed Assessment of Agencies’ Incorporation of OMB’s Data Center Requirements 27

16

Appendix III Comments from the Social Security Administration 50

17

Appendix IV GAO Contact and Staff Acknowledgments 51

18

Tables

19

Table 1: Office of Management and Budget’s (OMB) Five Requirements for Acquiring and Operating Federal Data Centers 10 Table 2: Agency-Reported Number of Existing and New Data Centers, as of March 2026 13 Table 3: Extent to Which Federal Agencies Incorporated the Office of Management and Budget’s Five Acquisition and Operational Requirements for their Data Centers, as of August 2026 14 Table 4: Evaluation Criteria Associated with the Office of Management and Budget’s (OMB) Requirements for Acquiring and Operating Federal Data Centers 25 Table 5: Extent to Which Department of Agriculture Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 27

20

Page i GAO-27-108971 Federal Data Centers

Page 4 of the original

21

Table 6: Extent to Which Department of Commerce Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 28 Table 7: Extent to Which Department of Defense (DOD) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 29 Table 8: Extent to Which Department of Energy Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 31 Table 9: Extent to Which Department of Health and Human Services (HHS) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 32 Table 10: Extent to Which Department of Homeland Security (DHS) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 33 Table 11: Extent to Which Department of Housing and Urban Development (HUD) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 34 Table 12: Extent to Which Department of the Interior Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 35 Table 13: Extent to Which Department of Justice Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 36 Table 14: Extent to Which Department of Labor Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 37 Table 15: Extent to Which Department of State Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 38

22

Page ii GAO-27-108971 Federal Data Centers

Page 5 of the original

23

Table 16: Extent to Which Department of Transportation Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 39 Table 17: Extent to Which Department of the Treasury Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 40 Table 18: Extent to Which Department of Veterans Affairs (VA) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 41 Table 19: Extent to Which Environmental Protection Agency (EPA) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 42 Table 20: Extent to Which National Aeronautics and Space Administration (NASA) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 43 Table 21: Extent to Which National Science Foundation (NSF) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 45 Table 22: Extent to Which Nuclear Regulatory Commission (NRC) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 46 Table 23: Extent to Which Office of Personnel Management (OPM) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 47 Table 24: Extent to Which Small Business Administration (SBA) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 48 Table 25: Extent to Which Social Security Administration (SSA) Addressed the Five Office of Management and Budget Acquisition and Operational Data Center Requirements, as of August 2026 49

24

Page iii GAO-27-108971 Federal Data Centers

Page 6 of the original

25

Abbreviations

26

CFO Act Chief Financial Officers Act of 1990 CIO Chief Information Officer DCIM Data Center Infrastructure Management DCOI Data Center Optimization Initiative DHS Department of Homeland Security DOD Department of Defense EPA Environmental Protection Agency FAA Federal Aviation Administration FDCCI Federal Data Center Consolidation Initiative FDCEA Federal Data Center Enhancement Act FISMA Federal Information Security Modernization Act FITARA Federal Information Technology Acquisition Reform Act GSA General Services Administration HHS Department of Health and Human Services HUD Department of Housing and Urban Development IT information technology NASA National Aeronautics and Space Administration NRC Nuclear Regulatory Commission NSF National Science Foundation OMB Office of Management and Budget OPM Office of Personnel Management SBA Small Business Administration SSA Social Security Administration TCSC Treasury Common Services Center VA Department of Veterans Affairs

27

This is a work of the U.S. government and is not subject to copyright protection in the United States. The published product may be reproduced and distributed in its entirety without further permission from GAO. However, because this work may contain copyrighted images or other material, permission from the copyright holder may be necessary if you wish to reproduce this material separately.

28

Page iv GAO-27-108971 Federal Data Centers

Page 7 of the original

29

Letter

30

441 G St. N.W. Washington, DC 20548

31

November 18, 2026

32

The Honorable Rand Paul, M.D. Chairman The Honorable Gary C. Peters Ranking Member Committee on Homeland Security and Governmental Affairs United States Senate

33

The Honorable James Comer Chairman The Honorable Robert Garcia Ranking Member Committee on Oversight and Government Reform House of Representatives

34

Federal agencies use data centers and cloud applications for their mission-critical data and operations. Data centers house computer servers, data storage systems, and network equipment that provide digital applications and services—such as artificial intelligence and cloud computing.1 Agencies are increasingly using digital services to make key processes more efficient, accessible, and scalable. The growing use of artificial intelligence among agencies will further increase demand for high-performance computing provided by data centers.

35

In December 2023, Congress, recognizing the growing need to ensure that data centers and cloud applications meet high standards for cybersecurity, resiliency, and availability, passed the Federal Data Center Enhancement Act (FDCEA), as part of the National Defense Authorization Act for Fiscal Year 2024.2 The FDCEA required, among other things, the Office of Management and Budget (OMB) to establish minimum requirements for new data centers and issue guidance for the 24 Chief

36

1According to the National Institute of Standards and Technology (NIST), cloud computing is a means for enabling on-demand access to shared pools of configurable computing resources (e.g., networks, servers, storage applications, and services) that can be rapidly provisioned and released.

37

2FDCEA modified the statutory authorization for the Federal Data Center Consolidation Initiative (now known as the Federal Data Center Optimization Initiative) under section 834 of the Federal Information Technology Acquisition Reform Act (FITARA), Pub. L. No. 113- 291, division A, title VIII, subtitle D, 128 Stat. 3292, 3444 – 3448 (Dec. 19, 2014) (44 U.S.C. § 3601 note). FDCEA extended the sunset date to October 1, 2026. Pub. L. No. 118-31, division E, title LIII, 137 Stat. 136, 940 (Dec. 22, 2023) (44 U.S.C. § 3601 note).

38

Page 1 GAO-27-108971 Federal Data Centers

Page 8 of the original

39

Financial Officers Act of 1990 (CFO Act) agencies to incorporate the requirements into the operations of their existing data centers.3

40

The FDCEA also included a provision for GAO to annually review and verify the compliance of federal agencies with OMB’s requirements for new and existing data centers. This third and final annual review responded to that statutory requirement.4 Our objective was to determine the extent to which federal agencies have incorporated OMB’s acquisition and operational requirements for data centers.

41

To address this objective, we sought information from the 24 CFO Act agencies. Three out of the 24 agencies (Department of Education, General Services Administration, and the U.S. Agency for International Development) stated that they do not have any data centers. As a result, they were not included in the analysis of compliance with OMB requirements. We analyzed OMB’s implementation guidance for the FDCEA, Memorandum M-25-03, issued on January 14, 2025, to identify the five requirements for federal agencies to incorporate when acquiring and operating agency-operated and contractor-operated data centers. We requested relevant data center documentation from all 21 agencies and analyzed the documentation, including policies, procedures, and risk management and security plans, from the agencies that provided it. In some cases, the agencies did not have the requested information. In addition, we obtained and analyzed responses from each of the 21 agencies to semi-structured questions describing each agency’s number of data centers and efforts to incorporate OMB’s requirements into their

42

3Unless otherwise noted, these requirements applied to the 24 federal agencies covered by FDCEA § 5302 (corresponding to the same agencies covered by the Federal Data Center Consolidation Initiative (now known as the Federal Data Center Optimization Initiative) in section 834(a)(2) of the Federal Information Technology Acquisition Reform Act (FITARA). The 24 agencies are the Departments of Agriculture, Commerce, Defense (DOD), Education, Energy, Health and Human Services (HHS), Homeland Security (DHS), Housing and Urban Development (HUD), the Interior, Justice, Labor, State, Transportation, the Treasury, and Veterans Affairs (VA); and the Environmental Protection Agency (EPA), General Services Administration (GSA), National Aeronautics and Space Administration (NASA), National Science Foundation (NSF), Nuclear Regulatory Commission (NRC), Office of Personnel Management (OPM), Small Business Administration (SBA), Social Security Administration (SSA), and U.S. Agency for International Development. These are also the same 24 departments and major agencies covered by the Chief Financial Officers Act of 1990, 31 U.S.C. § 901(b).

43

4This is the third and final of the three reviews, because the provisions of the FDCEA expired on October 1, 2026. The first review in 2024 and second review in 2025 resulted in briefings to congressional staff members on the status of OMB’s efforts to develop operational requirements and guidance for federal data centers and agencies’ efforts to incorporate these requirements.

44

Page 2 GAO-27-108971 Federal Data Centers

Page 9 of the original

45

data centers. We then compared agency documentation and responses to the requirements outlined in OMB Memorandum M-25-03. Specifically, we determined whether the evidence provided by the agencies addressed the evaluation criteria for each requirement. To determine an overall rating for each of the five requirements, we summarized the results of our assessments as:

46

• fully addressed—the agency fully addressed all of the requirement’s evaluation criteria;

47

• partially addressed—the agency fully or partially addressed some, but not all, of the requirement’s evaluation criteria; and

48

• not addressed—the agency did not address any of the requirement’s evaluation criteria

49

We supplemented our analysis with interviews and written communication with relevant agency officials to discuss the agencies’ progress in addressing these requirements, as appropriate. We also provided the results of our analysis of agency documentation to officials to corroborate our findings, collect additional evidence, and identify causes for any gaps we identified in agencies’ incorporation of the requirements. A more complete description of our objective, scope, and methodology is provided in appendix I.

50

We conducted this performance audit from February 2026 to November 2026 in accordance with generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objective. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objective.

51

Federal data centers are expected to provide secure, reliable, and highly Background available computing infrastructure to enable consistent access to federal information and information systems. Acquiring and operating these centers involves managing complex computing infrastructure, extensive cooling systems, and significant energy requirements.

52

The specific information technology (IT) infrastructure within a data center varies depending on the types of digital applications and services the data center supports. Generally, a data center contains servers, data storage drives, and networking equipment. The servers contain the hardware

53

Page 3 GAO-27-108971 Federal Data Centers

Page 10 of the original

54

responsible for large-scale computing power, and some data center facilities contain more than 5,000 servers.

55

The computing equipment inside a data center generates significant heat. To ensure that the equipment runs efficiently, cooling systems work to keep temperatures and humidity within proper ranges. These cooling systems use energy to pump water, cool the air, and remove heat from the IT equipment. As a result of their computing and cooling needs, data centers require substantial amounts of energy to operate. According to one energy research organization, it is not unusual to see new data centers being built with energy needs of 100 to 1000 megawatts, roughly equivalent to powering 80,000 to 800,000 households.5 On average, 40 to 50 percent of the energy used by a data center is for powering the IT infrastructure, and up to 40 percent is for cooling the equipment.6

56

IT Acquisition Reform Law Congress has emphasized the importance of reforming the government- Enhanced Data Center wide management of IT, and in December 2014 enacted federal IT reform provisions. These provisions are commonly referred to as the Federal Consolidation and Information Technology Acquisition Reform Act (FITARA) and were part Optimization Efforts of the Carl Levin and Howard P. ‘Buck’ McKeon National Defense Authorization Act for Fiscal Year 2015.7 Among other things, FITARA required federal agencies to:8

57

• submit to OMB a comprehensive inventory of the data centers owned, operated, or maintained by or on behalf of the agency;

58

5EPRI, Powering Intelligence: Analyzing Artificial Intelligence and Data Center Energy Consumption (May 28, 2024), https://www.epri.com/research/products/000000003002028905.

59

6Department of Energy, DOE Announces $40 Million for More Efficient Cooling for Data Centers (May 9, 2023), https://www.energy.gov/articles/doe-announces-40-million-more-efficient-cooling-data-centers.

60

7Pub. L. No. 113-291, division A, title VIII, subtitle D, 128 Stat. 3292, 3438 (Dec. 19, 2014).

61

8Pub. L. No. 113-291 § 834, 128 Stat. 3444–48 (44 U.S.C. 3601 note). Unless otherwise noted, these requirements apply to the 24 agencies specified in section 834 (corresponding to those agencies covered by the Chief Financial Officers Act of 1990. 31 U.S.C. § 901(b)).

62

Page 4 GAO-27-108971 Federal Data Centers

Page 11 of the original

63

• submit a multi-year strategy to achieve the consolidation and optimization of the agency’s data centers,9 to include performance metrics consistent with government-wide data center consolidation and optimization metrics; and

64

• report to OMB, on a quarterly basis, progress toward meeting government-wide data center consolidation and optimization metrics.

65

Additionally, the Federal Chief Information Officer (CIO) within OMB was tasked with establishing metrics for data center consolidation and optimization, ensuring public access to agencies’ progress, and developing annual goals for cost savings and optimization improvements through OMB’s Federal Data Center Consolidation Initiative (FDCCI).10

66

In August 2016, OMB issued Memorandum M-16-19, which established the Data Center Optimization Initiative (DCOI) and included guidance on how to implement the data center consolidation and optimization provisions of FITARA.11 In June 2019, OMB issued Memorandum M-19- 19, which updated the DCOI and redefined a data center as a purpose-built, physically separate, dedicated space that meets certain criteria.12 The memorandum also directed agencies to focus their efforts on their tiered data centers and to stop reporting on spaces not designed to be data centers (i.e., non-tiered data centers) as part of their inventory.13 The

67

9In lieu of submitting a data center inventory and strategy, the Department of Defense could submit this information as part of a defense-wide plan and report on cost savings, as required under §§ 2867(b)(2) and 2867(d) of the National Defense Authorization Act for Fiscal Year 2012.

68

10The sunset date for the data center provisions of FITARA was extended to October 1, 2022, and the statutory authorization for the provision has now lapsed. 44 U.S.C. 3601 note. The Federal Data Center Enhancement Act extended the sunset date to October 1, 2026.

69

11Office of Management and Budget, Data Center Optimization Initiative (DCOI), Memorandum M-16-19 (Washington, D.C.: Aug. 1, 2016).

70

12Office of Management and Budget, Update to Data Center Optimization Initiative (DCOI), Memorandum M-19-19 (Washinton, D.C.: June 25, 2019). According to OMB Memorandum M-19-19 and related reporting instructions, a data center generally is a purpose-built, physically separate, and dedicated space that contains one or more racks of servers, mainframes, and/or high-performance computers; has a dedicated uninterruptable power supply and/or backup generator for prolonged power outages; and/or has a dedicated cooling system or zone. Agencies are to report facilities matching these criteria as tiered data centers.

71

13OMB derived the term “tiered” and its definition from the Uptime Institute’s Tier Classification System. However, OMB notes that no specific certification is required in order for a data center to be considered tiered by OMB. According to OMB M-16-19, all data centers not marked as tiered should be considered non-tiered.

72

Page 5 GAO-27-108971 Federal Data Centers

Page 12 of the original

73

guidance outlined a process by which agencies could request, and OMB would approve, that these facilities no longer be reported.

74

Prior GAO Reporting on Since 2016, we have reported on OMB’s DCOI requirements for agencies and made recommendations to improve OMB’s oversight of DCOI.14 In Data Center Consolidation addition, since the enactment of FITARA, we have annually reviewed and Optimization Resulted agencies’ efforts to implement the data center provisions of FITARA and in Billions in Savings have published reports documenting the findings from each of these reviews.15 We noted that, while agencies were reporting progress toward DCOI data center closure, cost savings, and optimization goals, many agencies had incomplete optimization plans and were not meeting those goals. We made 126 recommendations from 2016 to 2021. Of the 126 recommendations, 101 have been implemented; 19 have been closed as not implemented; five were no longer valid; and one remains open. Specifically, as of July 2026, one recommendation to OMB related to revising its prior guidance to show agencies how to measure server utilization remains open.16 In February 2023, we reported that agencies had realized a cumulative total of $6.6 billion in cost savings and avoidances from fiscal years 2012 through 2021 related to data center consolidation and optimization.17

75

14GAO, Data Center Consolidation: Agencies Making Progress, but Planned Savings Goals Need to Be Established [Reissued on March 4, 2016], GAO-16-323 (Washington D.C.: Mar. 3, 2016); Data Center Consolidation: Reporting Can Be Improved to Reflect Substantial Planned Savings, GAO-14-713 (Washington, D.C.: Sept. 25, 2014); Data Center Consolidation: Strengthened Oversight Needed to Achieve Cost Savings Goal, GAO-13-378 (Washington, D.C.: Apr. 23, 2013); Data Center Consolidation: Agencies Making Progress on Efforts, but Inventories and Plans Need to Be Completed, GAO-12-742 (Washington, D.C.: July 19, 2012); and GAO-11-565.

76

15GAO, Data Center Optimization: Agencies Continue to Report Mixed Progress Against OMB’s Targets, GAO-22-105118 (Washington, D.C.: Mar. 8, 2022); Data Center Optimization: Agencies Report Progress, but Oversight and Cybersecurity Risks Need to Be Addressed, GAO-20-279 (Washington, D.C.: Mar. 5, 2020); Data Center Optimization: Additional Agency Actions Needed to Meet OMB Goals, GAO-19-241 (Washington, D.C.: Apr. 11, 2019); Data Center Optimization: Continued Agency Actions Needed to Meet Goals and Address Prior Recommendations, GAO-18-264 (Washington, D.C.: May 23, 2018); Data Center Optimization: Agencies Need to Address Challenges and Improve Progress to Achieve Cost Savings Goal, GAO-17-448 (Washington, D.C.: Aug. 15, 2017); Data Center Optimization: Agencies Need to Complete Plans to Address Inconsistencies in Reported Savings, GAO-17-388 (Washington, D.C.: May 18, 2017); and GAO-16-323.

77

16GAO, Data Center Optimization: Agencies Report Progress and Billions Saved, but OMB Needs to Improve Its Utilization Guidance, GAO-21-212 (Washington, D.C.: Mar. 4, 2021).

78

17GAO, Data Center Optimization: Agencies Continue to Report Progress, GAO-23-105946 (Washington, D.C.: Feb. 27, 2023).

79

Page 6 GAO-27-108971 Federal Data Centers

Page 13 of the original

80

Federal Data Center While the FITARA requirements led to the consolidation and optimization Enhancement Act of 2023 of federal data centers, the FDCEA of 2023 shifted the focus to ensuring high standards of cybersecurity, resiliency, and availability for the centers Called for OMB to that remain. Establish Minimum Requirements and Issue Congress acknowledged, in enacting the FDCEA, that the needs of the Implementation Guidance federal government with respect to data access and data processing systems have evolved since 2014. Given the significant efficiencies already achieved under FDCCI, Congress did not renew the expired provisions. Instead, it enacted the FDCEA, which struck the FDCCI provisions, and, among other things, directed OMB to set requirements for federal data centers to meet appropriate standards for cybersecurity, resiliency, and availability.

81

Specifically, the FDCEA required the following, among other things:

82

• The Administrator of the Office of Electronic Government within OMB (the Federal CIO) was to establish minimum requirements for new data centers, in consultation with the Administrator of General Services (i.e., head of the General Services Administration (GSA)), Director of the Cybersecurity and Infrastructure Security Agency within the Department of Homeland Security, National Cyber Director, and Federal CIO Council, by June 19, 2024.18 These minimum requirements were to include the following areas:

83

• ensuring the availability of new data centers

84

• evaluating the use of new data centers, focusing on facility costs, energy consumption, and related infrastructure

85

• establishing required uptime percentages19

86

• implementing protections against power failures, including on-site energy generation and access to multiple transmission paths

87

• ensuring protections against physical intrusions and natural disasters

88

18In our 2024 briefing to congressional staff members, we reported that OMB officials stated that they met with the General Services Administration Office of Government-wide Policy, Cybersecurity and Infrastructure Security Agency Interagency Security Committee, Federal Chief Information Officer Council, and Office of the National Cyber Director to discuss the development of data center requirements, as required by the Federal Data Center Enhancement Act.

89

19Uptime percentage is calculated as the number of available hours minus unplanned downtime.

90

Page 7 GAO-27-108971 Federal Data Centers

Page 14 of the original

91

• complying with information security protections as mandated by applicable laws and policy20

92

• incorporating any other requirements deemed appropriate by OMB

93

• OMB was to issue guidance, as appropriate, for the 24 CFO Act agencies to incorporate the requirements into the operations of any data centers by September 17, 2024.

94

• The 24 CFO Act agencies were to notify OMB and Congress during the development and planning lifecycle of new data centers and use technology in determining whether to establish new data centers or continue to operate an existing data center.

95

• OMB was to maintain a public-facing website that included information, data, and explanatory statements relating to the compliance of the 24 CFO Act agencies with these requirements. In maintaining the website, OMB was required to ensure that these agencies regularly, and not less frequently than biannually, updated the information related to their data centers.21

96

The provisions of the FDCEA sunset on October 1, 2026.

97

OMB’s Memorandum In January 2025, OMB issued Memorandum M-25-03, establishing both Established Requirements the minimum requirements and the implementation guidance to federal agencies related to the FDCEA.22 The memorandum was issued and Guidance for approximately seven months after the June 19, 2024, statutory deadline Acquiring and Operating to establish requirements, and approximately four months after the Federal Data Centers September 17, 2024, deadline to issue implementation guidance. The memorandum established updated standards for the acquisition, design, and management of federal data centers and centralized agency data center investment decisions.

98

In this memorandum, OMB defined that a data center was (1) composed of one or more permanent or semi-permanent structures, or a dedicated space within such a structure, that operates persistently in a fixed

99

20Subchapter II of chapter 35 of title 44, United States Code, establishes federal information security requirements, as enacted by the Federal Information Security Modernization Act of 2014.

100

21The last update on OMB’s public-facing website was July 2025. As of August 2026, there is no public-facing website with updates.

101

22Memorandum M-25-03 superseded prior data center policies, including the now-expired Data Center Optimization Initiative (DCOI).

102

Page 8 GAO-27-108971 Federal Data Centers

Page 15 of the original

103

location; (2) used for the housing of IT equipment, including servers, mainframe computers, high-performance computing devices, or data storage devices; and (3) actively used for the hosting of information and information systems that are accessed by other systems or by users on other devices.

104

The guidance further stated that it applied to agency-operated and contractor-operated data centers. Specifically, a data center was considered agency-operated if it was owned, operated, or maintained directly by a covered agency. This included facilities leased directly by an agency or those occupied under a General Services Administration occupancy agreement. A data center was considered contractor-operated if it was owned, operated, or maintained by a contractor on behalf of a covered agency. Contractor-operated data centers could include commercial co-location, in which an agency is one among many tenants.

105

Furthermore, the guidance also specified that some provisions of the memorandum applied differently depending on whether a given data center was new or existing.23 A data center was considered new if it was established or substantially upgraded or expanded after the date of the memorandum, January 14, 2025. Substantial upgrades or expansions were considered those involving the data center’s power supply or distribution, cooling, physical security, networking, IT equipment, or size of space hosting IT equipment. If a data center did not qualify as new, then it was considered an existing data center.

106

The memorandum also required agencies to assess gaps in their current data center capabilities and factor those into acquisition planning. According to OMB’s implementation guidance, agencies were to implement the acquisition and operational requirements into the management and planning of their data centers to ensure that federal data centers are secure, resilient, efficient, and mission ready. Table 1 describes the five OMB requirements for acquiring and operating federal data centers.

107

23OMB’s memorandum applied to both new and existing data centers for four of the five requirements. For the incorporating energy and water usage into decision-making requirement, OMB did not specifically require agencies to apply the provisions to existing data centers.

108

Page 9 GAO-27-108971 Federal Data Centers

Page 16 of the original

109

Table 1: Office of Management and Budget’s (OMB) Five Requirements for Acquiring and Operating Federal Data Centers

110

Requirement Description

111

Make key data center Given the criticality of data centers and the significant capital and ongoing investments required to decisions at the agency level acquire and manage them, agencies must centralize data center acquisition decision-making and operational management with the agency’s Chief Information Officer (CIO). Centralized oversight of the agency data center footprint will ensure the agency CIO can move toward the most efficient, reliable, and secure outcomes for the agency, while integrating data center and related information technology (IT) portfolio decision-making and planning into the requisite acquisition, budget, and programmatic processes. The requiring office and the relevant procurement official should consult with the agency’s CIO throughout the process of procuring a new data center or making substantial changes to an existing one. Agencies should use commercial co-location services rather than building new data centers to the extent that it is cost-effective and meets agency mission needs.

112

Monitor data center The timely and effective operation of data centers requires regular monitoring, management, and operations optimization of resources by data center operators through the collection and presentation of metrics. Automated tools, such as Data Center Infrastructure Management systems, can significantly improve the efficiency of a wide range of tasks: managing physical and virtual assets, monitoring equipment and power usage, metering energy consumption, and performing other core operational and planning functions. Use of automated tools and the data that they provide can reduce the costs associated with data centers. Agencies must incorporate automated tools, such as Data Center Infrastructure Management systems, into the management of all new data centers, including tools that monitor facilities-related data such as electrical consumption. For existing data centers, agencies should adopt the use of such tools to the extent that it is cost-effective.

113

Incorporate energy and Data centers consume significant amounts of energy and water to power and cool IT equipment. As water usage into decision- such, the cost, scarcity, and environmental impact of energy and water consumption necessitates that making agencies evaluate data centers against resource consumption metrics and best practices when making their decisions. Improved efficiency can reduce overall costs and increase reliability of data centers. While designing or planning a new data center, including any substantial upgrades to an existing data center, agencies are required to arrange for an assessment by specialists certified in data center energy efficiency to better understand the existing data center’s resource usage and recommend design considerations to achieve improved efficiencies. Agencies are required to review and consider the recommendations resulting from the assessment when making data center design or selection decisions, in coordination with the agency’s Chief Sustainability Officer and the agency’s facilities management representatives.

114

Meet mission availability To effectively enable agency missions, a data center must be able to meet the availability and uptime requirements needs of its hosted information systems despite a variety of planned and unplanned downtime situations, such as natural disasters and equipment failure. Agencies shall adopt a risk management-based approach to identify, reduce the likelihood of, and mitigate risks to the availability of data centers a Special Publications. This using frameworks such as National Institute of Standards and Technology approach includes implementing an internal control policy to determine and meet data center b availability (uptime) requirements using the results of a business impact analysis.

115

Page 10 GAO-27-108971 Federal Data Centers

Page 17 of the original

116

Requirement Description

117

Meet information and Data centers must be able to meet the reliability and resiliency needs of their hosted information and physical security information systems through implementation of appropriate information security and physical security c (FISMA), requirements protections. Effective implementation of the Federal Information Security Modernization Act including the appropriate use of National Institute of Standards and Technology frameworks and security controls, should guide agencies in protecting the information and information systems stored within a data center. Information systems used by a contractor to manage a data center should comply with the appropriate agency policy for managing risk in accordance with FISMA requirements. For both new and existing data centers, agencies must follow the Interagency Security Committeed risk management process to determine the physical security needs for each data center facility and to implement the appropriate standards for countermeasures. To complete the risk management process for physical security of the data center facility, agency CIOs must work in coordination with other senior officials for security and facilities management within their agency.

118

Source: GAO analysis of OMB Memorandum M-25-03. l GAO-27-108971

119

a The National Institute of Standards and Technology is the federal agency that develops information security standards and guidelines for federal information systems. b According to OMB Memorandum M-25-03, a business impact analysis identifies the impacts of information system downtime on agency missions and is part of an agency’s contingency planning processes, and relevant customer experience to determine the maximum tolerable duration and frequency of downtime events for each of the information sets and information systems hosted in a data center. c FISMA is a federal statute that establishes the framework for protecting federal information systems and requires agencies to develop, document, and implement agencywide information security programs. It also assigns agency heads the ultimate authority and responsibility to develop and implement agencywide information security programs. d The Interagency Security Committee is an interagency body that develops policies and standards for the security of nonmilitary federal facilities, while the Department of Defense has incorporated applicable standards into its facility-security policies and Unified Facilities Criteria.

120

OMB required agencies to have satisfied the five requirements for new and existing agency-operated data centers by January 14, 2026. For contractor-operated centers, compliance was expected by the later of the following two dates, (1) January 14, 2026, or (2) the date after January 14, 2025, that the contract was first renewed, extended, or replaced.24 The provisions in the OMB memorandum expired on September 30, 2026.

121

Agencies Reported the The 24 CFO Act agencies reported the number of federal data centers Number of New and they had as of March 2026. Three agencies (Education, GSA, and the U.S. Agency for International Development) reported that they had no Existing Data Centers new or existing data centers. The 21 remaining agencies collectively reported 1,392 data centers, of which 1,217 were agency-operated, 168 were contractor-operated, and seven were new.

122

24For contractor-operated data centers, the majority of agencies reported that compliance was expected by January 14, 2026.

123

Page 11 GAO-27-108971 Federal Data Centers

Page 18 of the original

124

Of the 21 agencies with data centers,

125

• Ten agencies (Department of Agriculture, Department of Defense (DOD), Department of Energy, Department of Health and Human Services (HHS), Department of Homeland Security (DHS), Department of the Interior, Department of Justice, Department of the Treasury, Department of Veterans Affairs (VA), and Office of Personnel Management (OPM)) reported having both agency and contractor-operated data centers;

126

• Three agencies (Department of Housing and Urban Development (HUD), National Science Foundation (NSF), and Small Business Administration (SBA)25) reported having no agency-operated data centers;

127

• Eight agencies (Department of Commerce, Department of Labor, Department of State, Department of Transportation, Environmental Protection Agency (EPA), National Aeronautics and Space Administration (NASA),26 Nuclear Regulatory Commission (NRC), and Social Security Administration (SSA)) reported having no existing contractor-operated data centers.

128

In addition, five agencies (Agriculture, Commerce, Energy, HHS, and NRC) reported having new data centers. For example, Commerce officials noted that it had a new contractor-operated data center. DOD reported that it was still determining whether it would have new data centers.27

129

Table 2 shows the agency-reported information on the number of existing agency-operated and contractor-operated data centers, and new data centers.

130

25In July 2026, SBA officials reported that all data centers are expected to close by the end of October 2026.

131

26According to NASA officials, it counted only agency-operated real property facilities with data hall rooms. During fiscal year 2026, the agency stated it plans to conduct a survey to identify any additional facilities that meet the OMB definition based on OMB M-25-03 and update its inventory accordingly.

132

27As of August 2026, DOD officials did not provide an update on the status of the number of new data centers.

133

Page 12 GAO-27-108971 Federal Data Centers

Page 19 of the original

134

Table 2: Agency-Reported Number of Existing and New Data Centers, as of March 2026

135

Number of existing data centers Number of new data centersa

136

Agency Agency-operated Contractor-operated

137

Department of Agricultureb 1 1 1

138

Department of Commerce 46 0 1

139

Department of Defense 477 11 To be determined

140

Department of Education 0 0 0

141

Department of Energy 28 79 1

142

Department of Health and Human Services 149 12 2

143

Department of Homeland Security 3 11 0

144

Department of Housing and Urban 0 2 0 Development

145

Department of the Interior 43 16 0

146

Department of Justice 9 4 0

147

Department of Labor 6 0 0

148

Department of State 140 0 0

149

Department of Transportation 16 0 0

150

Department of the Treasury 21 24 0

151

Department of Veterans Affairsc 250 2 0

152

Environmental Protection Agency 2 0 0

153

General Services Administration 0 0 0

154

National Aeronautics and Space 17 0 0 Administration

155

National Science Foundation 0 1 0

156

Nuclear Regulatory Commission 4 0 2

157

Office of Personnel Management 1 1 0

158

Small Business Administrationd 0 4 0

159

Social Security Administration 4 0 0

160

U.S. Agency for International Development 0 0 0

161

Total 1217 168 7

162

Source: GAO analysis of agency-provided data. I GAO-27-108971

163

a Agencies reported that the new data centers included either agency-operated or contractor-operated data centers. b Department of Agriculture officials stated that the agency will no longer have a federally owned data center after calendar year 2027. c Department of Veterans Affairs officials reported that the agency plans to close one of its existing contractor-operated data centers by November 30, 2026. d Small Business Administration officials stated that the agency plans to close all data centers by the end of October 2026.

164

Page 13 GAO-27-108971 Federal Data Centers

Page 20 of the original

165

OMB’s memorandum issued in January 2025 established minimum Federal Agencies requirements for acquiring and operating federal data centers as well as Varied in guidance for implementing the requirements. The five requirements for agencies to address were to (1) make key data center decisions at the Incorporating OMB’s agency level, (2) monitor data center operations, (3) incorporate energy Acquisition and and water usage into decision-making, (4) meet mission availability requirements, and (5) meet information security and physical security Operational requirements. As noted above, OMB required agencies to satisfy these Requirements for requirements by January 14, 2026, with potentially later dates for contractor-operated data centers. The requirements in the memorandum Their Data Centers expired on September 30, 2026.

166

Agencies varied in incorporating OMB’s five acquisition and operational requirements into the management and planning of their data centers.28 Specifically, as of August 2026, while none of the 21 agencies with reported data centers fully addressed all five requirements, nine agencies fully addressed half or more of the applicable requirements and 19 partially or fully addressed all of the applicable requirements.

167

Table 3 reflects the extent to which the 21 agencies with data centers incorporated the five acquisition and operational requirements into their data centers as of August 2026. In addition, appendix II provides more details on the assessment of each of the 21 agencies.

168

Table 3: Extent to Which Federal Agencies Incorporated the Office of Management and Budget’s Five Acquisition and Operational Requirements for their Data Centers, as of August 2026

169

Incorporate energy Meet information Make key data and water usage Meet mission and physical center decisions at Monitor data center into decision- availability security Agency the agency level operations making requirements requirements

170

Department of ◐ ◐ ◐ ◐ ◐ Agriculture

171

Department of ◐ ◐ ◐ ◐ ◐ Commerce Department of ● ● — ◐ ◐ Defense

172

Department of ◐ ◐ ◐ ◐ ◐ Energy

173

28Twenty-one agencies reported data centers and three agencies reported that they did not have data centers. The five OMB requirements were not applicable to those three agencies: Education, GSA, and the U.S. Agency for International Development.

174

Page 14 GAO-27-108971 Federal Data Centers

Page 21 of the original

175

Incorporate energy Meet information Make key data and water usage Meet mission and physical center decisions at Monitor data center into decision- availability security Agency the agency level operations making requirements requirements

176

Department of ◐ ◐ ◐ ◐ ◐ Health and Human Services Department of ● ● — ◐ ● Homeland Security Department of ◐ ● — ◐ ◐ Housing and Urban Development Department of the ● ◐ — ◐ ◐ Interior Department of ● ● — ● ◐ Justice Department of Labor ● ● — ◐ ◐ Department of State ● ● — ◐ ● Department of ● ● — ◐ ◐ Transportation Department of the ● ○ — ◐ ● Treasury

177

Department of ◐ ◐ — ◐ ◐ Veterans Affairs Environmental ◐ ● — ◐ ◐ Protection Agency

178

National Aeronautics ◐ ◐ — ◐ ◐ and Space Administration

179

National Science ◐ ◐ — ◐ ◐ Foundation Nuclear Regulatory ● ● ◐ ◐ ● Commission

180

Office of Personnel ◐ ◐ — ◐ ◐ Management Small Business ◐ ○ — ◐ ◐ Administration Social Security ● ● — ● ◐ Administration

181

● = Fully addressed—the agency fully addressed all of the requirement’s evaluation criteria. ◑ = Partially addressed—the agency fully or partially addressed some, but not all, of the requirement’s evaluation criteria. ○ = Not addressed—the agency did not address any of the requirement’s evaluation criteria. — = The requirement did not apply to the agency as it reported it had no new data centers and because the Office of Management and Budget did not specifically require agencies to apply the requirement to existing data centers. Source: GAO analysis of agency documentation. | GAO-27-108971

182

Page 15 GAO-27-108971 Federal Data Centers

Page 22 of the original

183

Note: The Office of Management and Budget required existing data centers to comply with some of the requirements only as practical or not at all. The Federal Data Center Enhancement Act directed that OMB “shall issue guidance to ensure, as appropriate, that covered agencies incorporate the minimum requirements established [for new data centers] into the operations of any data center for a covered agency existing as of the day of enactment [of the Act].”

184

Make key data center decisions at the agency level. Ten agencies fully addressed the requirement and 11 partially addressed the requirement. The 10 agencies that fully addressed the requirement were DOD, DHS, Interior, Justice, Labor, State, Transportation, Treasury, NRC, and SSA. For example, according to Interior’s Departmental Manual Part 112 Chapter 24 and Hosting Services Policy documents, data center acquisition decision-making and operational management are centralized with the Chief Information Officer (CIO), and the requiring office and procurement official coordinate with the CIO throughout the budget and acquisition process.

185

The 11 agencies that partially addressed the requirement were Agriculture, Commerce, Energy, HHS, HUD, VA, EPA, NASA, NSF, OPM, and SBA. For example:

186

• According to Energy officials, the agency has established an enterprise governance framework through which the CIO is actively engaged in the planning, budgeting, and execution of all IT acquisitions. However, these officials reported that 29 percent of Energy’s data centers had no CIO involvement. Energy officials said that these data centers operate under a decentralized governance structure in which program offices, rather than the centralized CIO organization, oversee IT management. Therefore, the agency has not sufficiently demonstrated that the requiring office and the relevant procurement official consult with the agency’s CIO throughout the process of procuring a new data center or making substantial changes to an existing one.

187

• HUD officials stated that the agency has centralized data center acquisition decision-making and operational management under its CIO. However, the documentation HUD provided did not demonstrate that the CIO is making key data center decisions at the agency level.

188

Monitor data center operations. Ten agencies fully addressed the requirement, nine partially addressed the requirement, and two did not address it.29 The agencies that fully addressed this requirement were

189

29DOD reported that the number of new data centers was to be determined. Therefore, we did not assess whether the agency incorporated automated tools into the management of all new data centers.

190

Page 16 GAO-27-108971 Federal Data Centers

Page 23 of the original

191

DOD, DHS, HUD, Labor, Justice, State, Transportation, EPA, NRC, and SSA. For example, for its existing data centers, according to the DOD Data Center Optimization Initiative memorandum, the Data Center Infrastructure Management (DCIM) system is the agency’s authoritative database for data center inventory reporting. It captures the current disposition of data center assets to include the type, location, size, and total physical and virtual server counts.

192

Nine agencies (Agriculture, Commerce, Energy, HHS, Interior, VA, NASA, NSF, and OPM) partially addressed this requirement. For example:

193

• While Commerce has draft memorandums that describe three of its components’ approaches to implementing monitoring capabilities for new and existing data centers, agency officials stated that the agency is issuing a Data Center Policy Memorandum. The memorandum will mandate the adoption of automated monitoring tools—including the DCIM systems—and set agencywide minimum monitoring standards for both new and existing data centers.30

194

• HHS provided examples of how its components incorporate automated tools, such as the DCIM systems, into the management of its data centers, including tools that monitor facilities-related data such as electrical consumption. However, the one component, Centers for Medicare & Medicaid Services, that reported new data centers did not provide any supporting documentation to demonstrate how the agency incorporated these tools into the management of the new data centers. Additionally, for its existing data centers, HHS did not provide supporting documentation demonstrating its use of such tools to the extent that it was cost-effective.

195

• For its existing data centers, NASA stated that it uses the DCIM system and other tools to monitor data centers. Also, the NASA CIO has funded implementation of a standard enterprise DCIM solution with centralized monitoring capabilities but has not yet implemented the enterprise solution. The agency expects to implement this solution in calendar year 2026, and a detailed project plan is currently being developed. According to NASA officials, DCIM is only required for new or substantially upgraded centers. However, the OMB requirement stated that for existing data centers, agencies should adopt the use of

196

30On October 16, 2026, while the report was at the agency for comment, the department finalized its data center policy to address compliance gaps and optimization, and strengthen alignment with OMB’s requirements, among other things. According to the policy, operating units and offices are required to implement the five OMB requirements, including the adoption of automated monitoring tools, within 90 business days.

197

Page 17 GAO-27-108971 Federal Data Centers

Page 24 of the original

198

such tools to the extent that it is cost-effective. NASA reported that it had no new data centers. Therefore, we did not assess whether the agency incorporated automated tools into the management of all new data centers. NASA officials did state that the agency plans to incorporate automated tools into the management of any new data centers approved in the future.

199

The remaining two agencies (Treasury and SBA) did not address this requirement. According to Treasury officials, operational monitoring is conducted through enterprise services and the bureau level management of data center environments, but the agency did not state whether it adopted the use of automated tools to do so. Additionally, SBA officials stated that it did not address this requirement because OMB’s memorandum was only related to new data centers. As previously mentioned, OMB’s guidance stated that for existing data centers, agencies should adopt the use of such tools to the extent that it is cost-effective.

200

Incorporate energy and water usage into decision-making. Five agencies (Agriculture, Commerce, Energy, HHS, and NRC) reported having new data centers, and all five partially addressed this requirement. For example:

201

• Agriculture relies on the System and Organization Controls for Service Organizations report for its contractor-operated data center. This report provides independent assurance over controls governing the contractor’s use of the DCIM system to facilitate the exchange and analysis of data from energy; lightning; fire safety; and heating, ventilation, and air conditioning systems. Agriculture officials also stated that the agency utilizes DCIM tools for monitoring energy usage in agency-operated data centers and incorporates data into decision-making. However, the department did not provide documentation to demonstrate that while designing its new data center, the agency arranged for an assessment by specialists certified in data center energy efficiency.

202

• NRC provided documentation identifying a certified Data Center Energy Practitioner currently employed by NRC. This individual serves as the Administrative Contracting Officer’s Representative for the Equinix co-location contracts and as the Office of the Chief Information Officer’s technical advisor for all data center-related projects. Additionally, NRC described how it considered an existing data center’s resource usage when making its design and selection decisions. However, the agency did not demonstrate how it

203

Page 18 GAO-27-108971 Federal Data Centers

Page 25 of the original

204

coordinates with the agency’s Chief Sustainability Officer and the agency’s facilities management representatives when reviewing and considering the assessment recommendations.

205

Sixteen agencies (DOD, DHS, HUD, Interior, Justice, Labor, State, Transportation, Treasury, VA, EPA, NASA, NSF, OPM, SBA, and SSA) reported that they did not have any new data centers for this reporting period, and thus, we did not assess their compliance for this requirement. Nonetheless, 13 agencies reported incorporating energy and water usage into decision-making for their existing data centers, even though OMB did not specifically require agencies to do so.

206

Meet mission availability requirements. Two agencies fully addressed the requirement, and the remaining 19 partially addressed the requirement. The agencies that fully addressed the requirement were Justice and SSA. For example, Justice’s Cybersecurity Program order and Information System Contingency Plan require components to define system availability requirements, implement contingency planning, and manage risks to ensure the availability and continuity of mission-critical information systems, which include data centers. Additionally, according to Justice’s Data Center Actions Information Technology Action memorandum, component CIOs operating data centers must establish a target availability of 99.8 percent for their data centers and report actual availability for the data centers on a semi-annual basis through a data call. The memorandum notes that risks affecting each data center’s availability must be identified and mitigated in accordance with Justice’s Information Systems Contingency Planning Guide.

207

Nineteen agencies (Agriculture, Commerce, DOD, Energy, HHS, DHS, HUD, Interior, Labor, State, Treasury, Transportation, VA, EPA, NASA, NSF, NRC, OPM, and SBA) partially addressed this requirement. For example:

208

• VA officials stated that the agency manages risk through a continuous authorization monitoring process that allows for the processing of risk management framework items such as authorities to operate and plans of action and milestones. While VA established a policy

209

Page 19 GAO-27-108971 Federal Data Centers