Delaware · Legislature · Bills
HB 233: An Act To Amend Title 26 Of The Delaware Code Relating To Large Energy Use Facilities.
Sponsors
Versions
What changed in this version
SPONSOR:
Rep. Burns & Rep. Heffernan & Rep. Minor-Brown & Sen. Hansen
Reps. Gorman, Phillips, Romer, Snyder-Hall, Griffith, S. Moore, Morrison, Lambert, Harris, Ortega; Sens. Sturgeon, Seigfried
HOUSE OF REPRESENTATIVES
153rd GENERAL ASSEMBLY
HOUSE SUBSTITUTE NO. 1
FOR
HOUSE BILL NO. 233
AS AMENDED BY
HOUSE AMENDMENT NO. 1 AS AMENDED BY HOUSE AMENDMENT NO. 1 TO HOUSE AMENDMENT NO. 1
AND
HOUSE AMENDMENT NO. 1
AND
HOUSE AMENDMENT NO. 3
AND
SENATE AMENDMENT NO. 2
[removed: ( ) a.] [added: ()a.] “Large energy use facility” means a facility that does [removed: either or both] [added: any] of the following:
1. Uses or is projected to use a monthly maximum demand of [removed: 50] [added: 75] megawatts or greater at a load factor of 85% or greater.
2. Uses a monthly maximum instantaneous demand of 100 megawatts or greater.
3. Uses or is able to use a monthly maximum demand of 30 megawatts or greater and is primarily engaged in providing a service described under code 518210 of the 2022 North American Industry Classification System.
b. Multiple facilities may be aggregated and treated as a large energy use facility for the purposes of this definition [removed: based on] [added: if the electric utility or the electric utility’s regulatory body determines they would pose reliability risks to the electric system because of their electricity use, proximity, and operational characteristics. Factors that may be considered include] close physical proximity, common ownership or control, or ownership or control through an affiliated company, [added: and] sharing of local electrical [removed: infrastructure,] [added: infrastructure.]
[added: c. “Large energy use facility” does not include a facility that stores, processes, refines, or transfers crude petroleum or petroleum products in bulk quantities, including refineries,] and [removed: reliability risks] [added: such uses shall not count toward aggregation. This exemption does not apply] to [added: a new facility that, after [the effective date of this Act] adds uses unrelated to] the [removed: electric system because] [added: storage, processing, refining, or transfer] of [removed: their size, proximity, and operational characteristics.] [added: crude petroleum, petroleum products in bulk quantities, or other energy storage materials, if the energy use of the new facility meets the thresholds in paragraph ()a. of this section.]
166 words unchanged, in 6 paragraphs
( ) “Load ramp period” means the period of time from commencement of service until a large energy use facility’s demand reaches the full contract capacity.
( ) “Contract capacity” means the amount of monthly peak load requirements that is mutually agreed to by a Commission-regulated electric utility and a large energy use facility for each month remaining in a contract term after the load ramp period has ended and for which both of the following apply:
a. The Commission-regulated electric utility agrees to provide retail electric service subject to the terms and conditions in its tariffs.
b. T he large load customer agrees to purchase service at that load level for the stated term of the contract under the same terms and conditions as those stated in the contract.
Section 2. Amend Subchapter II, Chapter 1, Title 26 of the Delaware Code by making deletions as shown by strike through and insertions as shown by underline as follows:
§ 203G. Approval of Electric Service Agreements for large energy use facilities.
(a) No person or entity may begin operations as a large energy use facility [added: served by a Commission-regulated electric utility] without first obtaining from the Commission the approval of an Electric Service Agreement (“ESA”) and entering into a Transmission [removed: Service] [added: Security] Agreement (“TSA”) with the Commission-regulated electric utility.
(b) [removed: A] [added: As a condition of receiving retail electric service by a Commission-regulated electric utility in the State, a] large energy use facility must negotiate the terms of an ESA [removed: and a TSA] with a Commission-regulated electric utility and thereafter the Commission-regulated electric utility must submit the ESA [removed: and TSA] for review and approval by the Commission. [added: As a further condition of receiving electric service in the State, there must be a transmission rate on file with the Federal Energy Regulatory Commission that, as to transmission costs, meets the objectives of subsection (c) of this section.] Notwithstanding any other provision of this title, Commission approval is required prior to any interconnection under a large energy user tariff promulgated by a Commission-regulated electric utility under the provisions of § 317 of this title.
(c) It is the intent of the General Assembly that residential retail electric customers and all other industrial and commercial customers, other than large energy use facilities, should not bear the financial costs or risks associated with large energy use facilities interconnecting to the electric system serving the State and that a regulatory framework be established to ensure large energy use facilities enter into agreements to directly assign these costs . Towards that end, t he Commission shall promulgate regulations to govern [added: tariffs subject to] the [removed: tariff] [added: review and approval of the Commission that are] applicable to large energy use [removed: facilities,] [added: facilities under the Commission’s jurisdiction,] and to set forth the minimum protective [removed: provisions] [added: features] required to be included in an ESA and [added: that must be included in the applicable transmission rate if] a [removed: TSA.] [added: large energy use facility is entitled to take retail service in the State.] The Commission regulations will identify specific form language to be incorporated into all [removed: ESAs and TSAs,] [added: ESAs,] and such language shall ensure the protections set forth in § 317 of this [removed: title .] [added: title.] At minimum, the ESA shall [removed: cover] [added: govern] the [removed: provision of] [added: terms and conditions under which] the [removed: retail electricity] [added: Commission-regulated electric utility will provide distribution] service, [removed: including, as applicable,] interconnection, cost [removed: allocation and obligation,] [added: allocation,] and risk mitigation [added: associated with serving the large energy use facility. The ESA may not require the procurement] of [removed: stranded or speculative costs] [added: electric supply service from the Commission-regulated electric utility] and [added: nothing in the ESA may restrict a large energy use facility from procuring electric supply service from a certified electric supplier. The ESA] must include all of the following provisions:
170 words unchanged, in 4 paragraphs
(1) Specify the duration of the contract, which must be a minimum of 10 years commencing after load ramp and a minimum of 15 years total including the load ramp period.
(2) Specify the date or estimated date that the Commission-regulated electric utility will begin to provide electricity service.
(3) Obligate the large energy use facility to pay a minimum amount or percentage of distribution charges, which cannot be less than 90% of contract capacity, based on the large energy use facility’s projected electricity usage for the electricity services the Commission-regulated electric utility is contracted to provide for the duration of the contract.
(4) For large energy use facilities that procure electricity from the Commission-regulated electric utility, obligate the large energy use facility to pay a minimum amount or percentage of supply costs, which cannot be less than 90% of contract capacity, based on the large energy use facility’s projected electricity usage for the electricity services the Commission-regulated electric utility is contracted to provide for the duration of the contract.
[removed: (5) Specify] [added: This paragraph does not apply to a large energy use facility] that [added: procures electric supply service from a certified electric supplier.]
[added: (5) Specify that, for purposes of calculating its retail service charges and for allocating among the retail customers of the utility those transmission charges paid by the utility in accordance with federal law and tariffs on file with the Federal Energy Regulatory Commission,] the large energy use facility’s annual capacity peak load contribution will be [added: deemed to have been] at least 90% of the contract capacity as adjusted by the applicable line loss factor and the large energy use facility’s annual network peak load contribution will be [added: deemed to have been] at least 90% of the contract capacity as adjusted by the applicable line loss factor.
(6) Specify the duration of the load ramp period [removed: (which cannot exceed 5 years)] during which a large energy use facility must reach full forecasted load and specify interim load levels the facility must meet at designated points during this period.
104 words unchanged, in 3 paragraphs
(7) Outline exit procedures that will apply to large energy use facility customers in the event of contract termination. Such procedures must include at least a 5-year advance notice of termination.
(8) Set exit fees that ensure the large energy use facility makes adequate contributions to offset all unrecovered costs in the event of contract termination.
(9) Require physical and operational readiness measures that facilitate targeted curtailment, including dedicated or otherwise segregable feeders where practicable; separation of any “critical” load segments behind the meter; and telemetry and communications capability sufficient for the Commission-regulated electric utility to execute and confirm curtailment actions during emergency operations.
(10) Establish enforceable curtailment and interruptibility obligations during emergencies and other circumstances determined by the [removed: Commission.] [added: Commission, Commission-regulated electric utility, or directed by the federal regional transmission system operator.]
(11) Require bonding [added: or] letters of credit backed by an investment-grade entity, or other cash-equivalent financial guarantees to ensure protection of other customers in the event of bankruptcy, liquidation, or other circumstances that would prevent the large energy use facility from meeting its obligations under the ESA.
Votes
History
Legislative data from LegiScan, used under the Creative Commons Attribution 4.0 license and arranged by Dorworth News.