A 3980: "Powering Up New Jersey Act"; establishes requirements for certain public utility infrastructure investments.
Sponsors
Versions
What changed in this version
ASSEMBLY COMMITTEE SUBSTITUTE FOR
ASSEMBLY, No. 3980
STATE OF NEW JERSEY
222nd LEGISLATURE
[removed: PRE-FILED FOR INTRODUCTION IN THE] [added: ADOPTED JUNE 4,] 2026 [removed: SESSION]
Sponsored by:
Assemblyman KEVIN P. EGAN
District 17 (Middlesex and Somerset)
Assemblywoman MARGIE DONLON, M.D.
District 11 (Monmouth)
SYNOPSIS
[removed: Requires electric] [added: “Powering Up New Jersey Act”; establishes requirements for certain] public [removed: utilities to develop and implement grid modernization plans.] [added: utility infrastructure investments.]
CURRENT VERSION OF TEXT
[removed: Introduced Pending Technical Review] [added: Substitute as adopted] by [removed: Legislative Counsel.] [added: the Assembly Telecommunications and Utilities Committee.]
An Act concerning [removed: the electric transmission] [added: certain public utility infrastructure investments] and [removed: distribution system,] supplementing Title 48 of the Revised [removed: Statues, and amending P.L.1999, c.23 and P.L.2007, c.340.] [added: Statutes.]
Be It Enacted by the Senate and General Assembly of the State of New Jersey:
1. [removed: (New section) As used in sections 1 through 4 of P.L. , c. (C. ) (pending before the Legislature as this bill):]
"Board" means the Board of Public Utilities.
"Distributed energy resource" means an electricity-producing resource or controllable load that is connected to an electric public utility’s distribution infrastructure.
"Electric public utility" means the same as the term is defined in section 3 of P.L.1999, c.23 (C.48:3-51).
[removed: "Grid Modernization Plan," or "plan," means the plan prepared by each electric public utility pursuant to section 2 of P.L. , c. (C. ) (pending before the Legislature as this bill),] [added: This act shall be known] and [removed: implemented pursuant to section 3 of P.L. , c. (C. ) (pending before the Legislature] [added: may be cited] as [removed: this bill).] [added: the “Powering Up New Jersey Act.”]
2. [removed: (New section)] a. [removed: No later than one year after the effective date of] [added: As used in] this [removed: act, each] [added: section:]
“Board” means the New Jersey Board of Public Utilities or a successor agency.
[added: “Customer-generator facility” means a customer-generator facility, as that term is defined pursuant to N.J.A.C.14:8-5.1 or it successor, that is eligible for a level 1 interconnection review by an] electric public utility [added: pursuant to N.J.A.C.14:8-5.4 or its successor or a level 2 interconnection review by an electric public utility pursuant to N.J.A.C.14:8-5.5 or its successor.]
“Distributed energy resource” means distributed generation, energy storage systems, electric vehicles, microgrids, fuel cells and demand-side management measures, including energy efficiency, demand response, and demand flexibility, that are deployed at the distribution level on either the customer or utility side of the meter.
[added: “Electric public utility” means the same as the term is defined] in [removed: the State shall prepare and submit to the board a Grid Modernization Plan. The purpose of the plan shall be to identify the most beneficial, cost-efficient, and practicable projects, to be undertaken by the electric public utility pursuant to] section 3 of [removed: P.L. , c. (C. ) (pending before the Legislature as this bill), to modernize the State's electric distribution system within the utility's service area.] [added: P.L.1999, c.23 (C.48:3-51).]
[removed: b. A plan may include, but shall] [added: “Energization” or “energize” means connecting new customers to the electric distribution system, establishing adequate load capacity to provide electric public utility service to a new customer, or upgrading electric capacity to provide electric public utility service to an existing customer. “Energization” or “energize” does] not [removed: be limited to, projects that:]
[removed: (1) integrate energy storage systems into] [added: include activities relating to] the [removed: electric distribution system;] [added: interconnection of electricity supply resources.]
[removed: (2) increase] [added: “Energization time period” means] the [removed: capacity] [added: period] of [removed: the] [added: time between when an] electric [added: public utility receives a request for] distribution [removed: system] [added: service and when the distribution service is installed and energized.]
[added: “Flexible interconnection or energization tariff” means a way] to [added: energize a new load or] interconnect [added: a] distributed energy [removed: resources;]
[removed: (3) prepare the] [added: resource to an] electric [added: public utility’s] distribution system [added: without necessitating immediate modifications] to [removed: deliver power in accordance with] the [removed: State's greenhouse gas emissions goals;]
[removed: (4) decrease] [added: distribution system, which energization or interconnection is governed by a set of rules and requirements and includes an agreement for curtailing] the [removed: risk] [added: import or export] of [removed: power outages, particularly outages caused] [added: electricity from and to the distribution system at certain times or operation conditions] by [removed: storms] [added: use of certified power control systems] or other [removed: adverse weather events;] [added: load management technologies.]
[removed: (5) improve] [added: “Hosting capacity” means] the [removed: resilience] [added: amount] of [added: electric generation that can be interconnected to] the electric distribution system [removed: against natural hazards associated with climate change, including increased temperatures] [added: at a given time] and [removed: flood risk;] [added: at a given location under existing electrical grid conditions] and [added: operations without adversely impacting safety, power quality, reliability, or other operational criteria.]
[removed: (6) otherwise improve] [added: “Interconnection time period” means] the [removed: ability of] [added: elapsed time between:]
[added: (1) when an electric public utility receives a substantially-complete interconnection application for a customer-generator facility and when] the [added: utility issues a signed part 1 interconnection agreement, as established by the board; and]
[added: (2) when an] electric public utility [added: receives confirmation of the construction official’s successful inspections and permit closing for a customer-generator facility and when the facility is granted permission] to [added: operate.]
“Load capacity” means the amount of load that can be added to the electric distribution system at a given time and at a given location under existing electrical grid conditions and operations without adversely impacting safety, power quality, reliability, or other operational criteria.
[added: b. To] provide [removed: uninterrupted] [added: safe, adequate, and proper] electric [removed: power] [added: public utility service, an electric public utility shall:]
(1) conduct sufficient advanced planning, engineering, and construction of electric distribution system hosting capacity and load capacity and sufficient preordering of transformers and other needed equipment so that electric public utility customers can be energized and interconnected without substantial delay; and
[added: (2) upgrade its electric distribution system as needed and in time] to [removed: customers, given] [added: allow for] the [removed: foreseeable changes in physical] [added: achievement of federal, State, regional,] and [removed: market conditions.] [added: local air quality and decarbonization standards, plans, and regulations, including vehicle emissions standards.]
c. [removed: A plan] [added: An electric public utility] shall include [removed: a cost estimate for each project included in] [added: infrastructure investments needed to comply with subsection b. of this section as part of] the [removed: plan and an appropriate timeline for] [added: utility’s Infrastructure Investment Program filed pursuant to sections 3 through 10 of P.L. , c. (C. through C. ) (pending before] the [removed: plan's implementation.] [added: Legislature as this bill).]
d. [removed: No later than] [added: Within] 240 days [removed: after receipt] of [removed: a Grid Modernization Plan,] the [removed: board shall approve, conditionally approve, or disapprove the plan and provide written notice] [added: date] of [removed: the determination to the electric public utility. The board shall assess a plan on the basis] [added: enactment] of [removed: its ability to achieve] [added: P.L. , c. (C. ) (pending before] the [removed: objectives enumerated in subsections a. and b. of this section, in addition to the plan’s feasibility, cost effectiveness, and expected ratepayer impact considering all available revenue streams. If the board does not provide written notice of the determination made pursuant to this subsection, the plan shall be deemed to have been approved, and the electric public utility shall proceed to implement the plan] [added: Legislature] as [removed: provided by paragraph (1) of subsection e. of] this [removed: section.]
[removed: e. (1) If a Grid Modernization Plan is approved, the] [added: bill), an] electric public utility shall [removed: implement the approved plan within 90 days after receipt of the board’s written notice or after the expiration of the 120-day period established by subsection d. of this section, as the case may be, or within another timeframe agreed to by the board.]
[removed: (2) If a plan is conditionally approved, the board’s written notice shall specify the conditions that are to be satisfied in order for the plan to be deemed approved pursuant to this section. The electric public utility shall implement the conditionally approved plan, in accordance] [added: file] with the [removed: conditions specified in the notice, either within 90 days after receipt of the board’s notice or within another timeframe agreed to by the board.] [added: board for approval:]
[removed: (3) If a plan is disapproved, the board’s written notice shall be accompanied by a] [added: (1)] detailed [removed: statement describing] [added: mapping of electric distribution hosting capacity and available load capacity and any underlying data with appropriate safeguards to protect confidentiality and critical infrastructure;]
[added: (2) proposed reasonable average and maximum target energization time periods that may vary depending on] the [removed: reasons] [added: nature of the work required and factors beyond the electric public utility’s control, along with a record of recent energization time periods] for [removed: disapproval. Not more] [added: various customer rate classifications and voltage service levels;]
(3) a record of recent interconnection time periods for customer-generator facilities, broken out by whether the facilities meet screening criteria and other relevant attributes, as proposed by an electric public utility and approved by the board;