New Jersey · A 3980
New Jersey A 3980: what changed from Introduced to Comm Sub
What changed in this version
[added: (4) proposed reasonable average and maximum target interconnection time periods for customer-generator facilities. However, the targets shall be less] than [removed: 30 days after receipt] [added: the electric public utility’s recent interconnection time periods, submitted pursuant to paragraph (3)] of [added: this subsection, and] the [removed: board’s notice,] [added: interconnection time periods specified in regulations adopted under subchapter 5 of chapter 8 of title 14 of] the [added: New Jersey Administrative Code;]
(5) a plan to automate the processing of interconnection applications to instantly issue signed part 1 interconnection agreements, as established by the board, for any customer-generator facility that is eligible for level 1 interconnection review pursuant to N.J.A.C.14:8-5.4 or its successor and meets all relevant screening criteria for such review;
(6) optional flexible interconnection or energization tariffs;
[added: (7) a plan to use distributed energy resources, which may include performance-based compensation for aggregated distributed energy resources, to avoid or minimize the need for traditional] electric [added: distribution system upgrades where feasible; and]
(8) commercial and industrial rates designed for high-voltage electric vehicle charging applications, taking into account alternatives to traditional demand-based charges that appropriately recover the marginal costs associated with such applications.
[added: e. An electric] public utility shall [removed: submit] [added: publish the information in paragraph (1) of subsection d. of this section on its Internet website so the information is accessible to customers, stakeholders, and verified third parties and shall, at] a [removed: revised Grid Modernization Plan] [added: minimum, update the information on a quarterly basis.]
[added: f. An electric public utility shall publish the energization time periods adopted pursuant] to [added: paragraph (2) of subsection d. of this section, and] the [added: interconnection time periods adopted pursuant to paragraph (3) and (4) of subsection d. of this section, on its Internet website so the information is accessible to customers. An electric public utility shall make such information available in any other manner and by any other means as directed by the board.]
[added: g. In an Infrastructure Investment Program, and in a base rate case, an electric public utility shall report to the] board, and the [added: Department of Labor and Workforce Development, its current qualified staffing levels for each job classification needed to achieve the requirements of this section. In its report, the electric public utility shall include a review of anticipated needs for future electric public utility, affiliate, and contractor personnel.]
[added: h. An electric public utility shall provide an energization and interconnection report to the] board [added: at least annually, which report] shall [removed: approve, conditionally approve,] [added: contain the following information:]
(1) the utility’s average and median energization time period and the standard deviation for such time periods;
[added: (2) the utility’s average and median interconnection time period for customer-generation facilities and the standard deviation for such time periods, broken out by whether the facilities meet screening criteria] or [removed: disapprove] [added: other relevant attributes, as proposed by an electric public utility and approved by] the [removed: revised plan in accordance] [added: board;]
[added: (3) an explanation for any energization time period or interconnection time period that exceeds the utility’s most recent maximum targets for such time periods, as filed] with [added: the board pursuant to either paragraph (2) or paragraph (4) of subsection d. of this section and as approved by the board; and]
(3) a strategy for meeting any missed targets for energization time periods and interconnection time periods in the future.
i. To reflect changed circumstances and new information, and to achieve the goal of shortening energization time periods and interconnection time periods over time, the board shall periodically update the energization time periods and interconnection time periods submitted by an electric public utility pursuant to either paragraph (2) or paragraph (4) of subsection d. of this section and the energization and interconnection report requirements prescribed under subsection h. of this section.
j. The board may establish performance incentives or penalties and may require an electric public utility to take remedial actions to achieve the requirements of this section. However, the board shall establish penalties for repeated violations of the requirements adopted pursuant to this section, including for failure to undertake remedial actions authorized pursuant to this subsection, and other relevant requirements adopted by the board.
[added: k. The board may adopt rules and regulations, pursuant to the “Administrative Procedure Act,” P.L.1968, c.410 (C.52:14B-1 et seq.), as may be necessary to effectuate] the provisions of this section.
3. [removed: (New section) a. No later than 90 days after a Grid Modernization Plan receives approval,] [added: As used in sections 3 through 10 of P.L. , c. (C. through C. ) (pending before the Legislature as this bill):]
[added: “Board” means the New Jersey Board of Public Utilities] or [added: any successor agency.]
[added: “Gas public utility” means a public utility, as that term is defined in R.S.48:2-13, that distributes gas to end users] within [removed: another timeframe agreed] [added: the State.]
[added: “In service” means when a project approved for inclusion in a public utility’s Infrastructure Investment Program is functioning in its intended purpose, has finished construction and is actively in use, and is actively helping the public utility] to [added: provide efficient public utility service.]
[added: “Program” means the Infrastructure Investment Program established] by the board pursuant to [removed: section 2 of P.L. , c. (C. ) (pending before the Legislature as this bill), the electric public utility shall commence implementing the plan. The plan shall be fully implemented within the timeframe specified in the plan pursuant to] subsection [removed: c.] [added: a.] of section [removed: 2] [added: 4] of P.L. , c. (C. ) (pending before the Legislature as this bill). [removed: In]
[added: “Public utility” means] the [removed: event] [added: same as] that [removed: an electric public utility] [added: term] is [removed: unable] [added: defined pursuant] to [removed: fully implement its plan,] [added: R.S.48:2-13.]
[added: “Water public utility” means either: (1) an investor-owned public utility that provides water public utility service; or (2) a municipal public utility that provides water utility service to more than 1,000 billed customers in another municipality and charges a different rate to customers within the municipality than] it [removed: shall provide written notice] [added: charges] to [removed: this effect to the board.]
[removed: b. Subject to review by the board, an electric public utility shall be entitled to full and timely cost recovery for all costs incurred in the implementation] [added: customers outside] of [removed: its plan.] [added: the municipality.]
4. [removed: (New section)] a. [removed: No later than one year after the effective date of this act, the board shall develop a program to provide grants to electric public utilities for the purpose of providing financial relief to ratepayers for rate increases caused by the implementation of a Grid Modernization Plan.]
[removed: b.] The [removed: board shall develop priority ranking criteria for the award of grants under the program. The priority ranking criteria shall provide additional priority for a project that receives funding pursuant to the federal "Infrastructure Investment and Jobs Act," Pub.L.117-58, or the federal “Inflation Reduction Act,” Pub.L.117-169.]
[removed: c. There is established in the] Board of Public Utilities [added: shall permit, through] a [removed: special, nonlapsing fund] [added: program] to be known as [removed: the Grid Modernization Ratepayer Relief Fund. Moneys] [added: an Infrastructure Investment Program, a public utility to accelerate its investment] in the [removed: fund shall be used by the board solely for the purpose] [added: construction, installation, and rehabilitation] of [removed: administering the grant program developed pursuant to this section. The fund shall be administered by the board] [added: certain public utility plants] and [removed: shall be credited with:]
[removed: (1) moneys] [added: facilities] that [removed: are appropriated into] [added: enhance safety, reliability, and resiliency or support economic growth and] the [removed: fund by the Legislature;]
[removed: (2) moneys received from the societal benefits charge established pursuant to] [added: achievement of applicable federal, State, regional, and local air quality and decarbonization standards, including, but not limited to, standards prescribed in] section [removed: 12] [added: 2] of [removed: P.L.1999, c.23 (C.48:3-60),] [added: P.L. , c. (C. ) (pending before the Legislature] as [removed: deemed appropriate by] [added: this bill). The purpose of an Infrastructure Investment Program shall be to provide a rate recovery mechanism that encourages and supports necessary accelerated construction, installation, and rehabilitation of certain public utility plants and equipment. As set forth in sections 3 through 10 of P.L. , c. (C. through C. ) (pending before] the [removed: board;]
[removed: (3) moneys made available] [added: Legislature as this bill), such investment shall occur in a systematic and sustained way] to [added: advance construction, installation, and rehabilitation of public utility infrastructure needed for continued system safety, reliability, and resiliency and for sustained economic growth in] the [removed: board pursuant] [added: State of New Jersey.]
[added: b. Through the Infrastructure Investment Program, a public utility may obtain accelerated recovery of qualifying investments, subject] to the [removed: implementation] [added: terms] of [added: sections 3 through 10 of P.L. , c. (C. through C. ) (pending before] the [removed: Regional Greenhouse Gas Initiative] [added: Legislature as this bill),] and [removed: P.L.2007, c.340 (C.26:2C-45 et seq.); and]
[removed: (4)] any [removed: return on] [added: other conditions set by the board in approving a public utility’s Infrastructure Investment Program. To participate in the program, a public utility shall apply to the board in a manner and form determined by the board.]