SECTION 6.(b) This section is effective when it becomes law and applies to data centers for which no local development approvals or State permits, certifications, or authorizations have been issued for siting of the data center on or before that date. This section shall not be construed to impair agreements for incentives executed on or before that date. PART II. ENERGY POLICY PROVISIONS
[removed: COST CAP] [added: UTILITIES COMMISSION TO DELAY COMPLIANCE WITH CEPS REQUIREMENT]
[added: THROUGH USE OF SWINE WASTE RESOURCES] FOR [removed: CEPS SET-ASIDES] [added: ELECTRIC MEMBERSHIP]
CO-OPERATIVES AND MUNICIPAL ELECTRIC PROVIDERS
SECTION [removed: 7.(a)] [added: 7. The Utilities Commission shall delay the required compliance with] G.S. [removed: 62-133.8 reads as rewritten:]
[removed: "§ 62-133.8. Clean Energy] [added: 62-133.8(e) by the Electric Membership Co-operatives] and [removed: Energy Efficiency Portfolio Standard (CEPS).]
[removed: (d) Compliance With CEPS Requirement Through Use of Solar Energy Resources. – For calendar year 2018 and] [added: Municipal Electric Providers (the Systems) until January 1, 2029, unless the systems request the ability to execute a contract] for [removed: each calendar year thereafter,] [added: this purpose] at [removed: least two-tenths of one percent (0.2%) of the total electric power in kilowatt hours sold to retail electric customers in the State, or] an [removed: equivalent amount of energy,] [added: earlier date. No later than January 1, 2029, the Commission] shall [removed: be supplied by] [added: initiate] a [removed: combination of new solar electric facilities and new metered solar thermal energy facilities that use one or more of the following applications: solar hot water, solar absorption cooling, solar dehumidification, solar thermally driven refrigeration, and solar industrial] process [removed: heat. The terms] [added: to review the reasonableness] of [removed: any] [added: the proposed costs of the associated renewable energy credits, and the costs to be passed on to the ratepayers, prior to the execution of a] contract [removed: entered into] between [removed: an electric power supplier and a new solar electric facility or new metered solar thermal energy facility shall be of sufficient length to stimulate development of solar energy; provided,] the [removed: Commission shall develop a procedure to determine if an electric power supplier is in compliance with the provisions of this subsection if a new solar electric facility or a new metered solar thermal energy facility fails to meet the terms of its contract with the electric power supplier. As used in this subsection, "new" means a facility that was first placed into service on or after January 1, 2007. The electric power suppliers shall comply with the requirements of this Page 8 Senate Bill 730-Fourth Edition subsection according to the following schedule:schedule, if the incremental costs to comply with this subsection do not exceed two hundred percent (200%) of the cost to supply, or contract for supply, an equivalent percentage of total electric power in kilowatt hours sold to retail electric customers in the State using any other clean energy resource: Calendar Year Requirement for Solar Energy Resources 2010 0.02% 2012 0.07% 2015 0.14% 2018 0.20%]
[removed: (e) Compliance With CEPS Requirement Through Use of Swine Waste Resources. – For calendar year 2018] [added: systems] and [removed: for each calendar year thereafter, at least two-tenths of one percent (0.2%) of the total electric power in kilowatt hours sold to retail electric customers in the State shall be supplied, or contracted for supply in each year, by] [added: a] swine [removed: waste. The electric power suppliers, in the aggregate, shall comply with the requirements of this subsection according to the following schedule:schedule, if the incremental costs to comply with this subsection do not exceed two hundred percent (200%) of the cost to supply, or contract for supply, an equivalent percentage of total electric power in kilowatt hours sold to retail electric customers in the State using any other clean energy resource:]
Calendar Year Requirement for Swine Waste Resources 2012 0.07% 2015 0.14% 2018 0.20%
[removed: (f) Compliance With CEPS Requirement Through Use of Poultry Waste Resources. – For calendar year 2014 and for each calendar year thereafter, at least 900,000 megawatt hours of the total electric power sold to retail electric customers in the State or an equivalent amount of energy shall be supplied, or contracted for supply in each year, by poultry] waste [removed: combined with wood shavings, straw, rice hulls, or other bedding material. The electric power suppliers, in the aggregate, shall comply with the requirements] [added: generator. Reasonableness] of [removed: this subsection according to] the [removed: following schedule:schedule, if the incremental] costs [removed: to comply with this subsection do not exceed two hundred percent (200%) of the cost to supply, or contract for supply, an equivalent amount of megawatt hours sold to retail electric customers in the State using any other clean energy resource:]
Calendar Year Requirement for Poultry Waste Resources 2012 170,000 megawatt hours 2013 700,000 megawatt hours 2014 900,000 megawatt hours
(m) An electric power supplier shall satisfy the requirements of subsections (b) and (c) of this section, as applicable, in compliance with current law and practice with respect to the least cost planning for generation, pursuant to G.S. 62-2(a)(3a), in a manner that maintains or improves upon the adequacy and reliability of the existing grid. Through application of least cost principles to the requirements of this section, it is the goal of the General Assembly that the cap on per account annual charges set forth in subdivision (4) of subsection (h) of this section shall be reduced by fifty percent (50%) for all customer classes by 2035."
[removed: SECTION 7.(b) Nothing in this section shall be construed to impair any contract executed on or before July 1, 2026, for purposes of complying with the requirements of G.S. 62-133.8 as it existed prior to amendments enacted by subsection (a) of this section. All reasonable and prudent incremental costs incurred by an electric power supplier to comply with any former requirement of G.S. 62-133.8 may be recovered as provided in G.S. 62-133.8(h). For the purposes of cost recovery under this section, reasonable and prudent incremental costs shall] [added: being proposed should] include [removed: all of] the [removed: following:]
Senate Bill 730-Fourth Edition Page 9
[removed: (1) Costs under purchase contracts for clean energy resources entered into prior to July 1, 2026, for the purpose] [added: costs] of [removed: complying with the clean] [added: other renewable] energy [removed: portfolio standard requirements.]
[removed: (2)] [added: credits.] The [added: systems shall not pass along any] costs [removed: of clean energy facilities built or acquired by an electric power supplier for which a certificate of public convenience and necessity has been issued] [added: to the ratepayers deemed] by the Commission [removed: prior] to [removed: July 1, 2026.] [added: be unreasonable.]
RFP FOR STUDY OF UTILITY POLICIES TO INCREASE AFFORDABILITY OF
ELECTRIC RATES
SECTION 8. Recognizing the rising costs of utility service, the General Assembly finds that an examination of various utility policies should be conducted to ensure these policies are not exacerbating affordability issues for citizens of the State, including the 2050 goal for a reduction in carbon dioxide (CO2) emitted in the State from electric generating facilities that results in carbon neutrality, pursuant to G.S. 62-110.9. In addition to examining these existing utility policies, the General Assembly finds that expert analysis should be performed to determine the most effective approach to ensuring that costs of utility service to large load customers is not borne by other residential, commercial, and industrial customers in North Carolina, including appropriate terms for a large load tariff. The [removed: Legislative Services Officer] [added: North Carolina Collaboratory (Collaboratory)] shall issue a request for proposals for a study to be conducted by an entity with nationally recognized expertise in research and analysis of utility policy and rates to (i) ascertain the current impacts, and projected impacts over the next 25 years, to residential, commercial, and industrial customer bills from the 2050 carbon neutrality goal, and whether any changes to this policy or other policies are advisable to enhance customer affordability and (ii) provide recommendations for effective policies to prevent rate impacts from large load customers on other customer classes, including requirements that large load customers generate a portion of their own power, as well as curtailment policies for large load customers. The study shall adhere to the following time line:
(1) The request for proposals (RFP) shall be issued on or before August 1, 2026.
(2) A contract to award the RFP shall be executed on or before November 1, 2026.
(3) The study shall be completed and submitted to the Joint Legislative Commission on Energy Policy on or before May 1, 2027, in order to inform the development of utility policy during the 2027 Regular Session. The Utilities Commission and the Public Staff shall assist the (i) [removed: Legislative Services Officer,] [added: Collaboratory,] as needed, in [added: the] development of the RFP and the selection of a contractor and (ii) selected contractor, in every permissible manner within the constraints of their respective authority, in the conduct of the study.
EXPRESS PERMIT REVIEW FOR ENERGY PROJECTS
SECTION 9.(a) G.S. 143B-279.13 reads as rewritten:
"§ 143B-279.13. Express permit and certification reviews.
Legislative data from LegiScan, used under the Creative Commons Attribution 4.0 license and arranged by Dorworth News.