(a) The Department of Environmental Quality shall develop an express review program to provide express permit and certification reviews in all of its regional offices. Participation in the express review program is voluntary, and the program shall be supported by the fees determined pursuant to subsection (b) of this section. The Department of Environmental Quality shall determine the project applications to review under the express review program from those who request to participate in the program. The express review program may be applied to any one or all of the permits, approvals, or certifications in the following programs: the erosion and sedimentation control program, the coastal management program, and the water quality programs, including water quality certifications and stormwater management. The express review program shall focus on the following permits or certifications: [added: Senate Bill 730-Fifth Edition Page 9]
(1) Stormwater permits under Part [removed: 1] of Article 21 of Chapter 143 of the General Statutes.
Page 10 Senate Bill 730-Fourth Edition
539 words unchanged, in 8 paragraphs
(2) Stream origination certifications under Article 21 of Chapter 143 of the General Statutes.
(3) Water quality certification under Article 21 of Chapter 143 of the General Statutes.
(4) Erosion and sedimentation control permits under Article 4 of Chapter 113A of the General Statutes.
(5) Permits under the Coastal Area Management Act (CAMA), Part 4 of Article 7 of Chapter 113A of the General Statutes.
(a1) The Department of Environmental Quality shall have the authority to create express permitting options for programs in addition to those listed in subsection (a) of this section where it deems there to be a need or where it determines an express permitting option would create greater efficiencies for the permitting process.
(a2) The Department of Environmental Quality shall create an express review program for all permits, authorizations, and certifications required from the Department for projects involving the generation, distribution, or transmission of energy or fuel, including natural gas, diesel, petroleum, or electricity. Participation in the express review program is voluntary.
(b) The Department of Environmental Quality shall set the fees for express application review under the express review program at a level sufficient to cover all program expenses. Notwithstanding G.S. 143-215.3D, the maximum permit application fee to be charged under subsection (a) of this section for the express review of a project application requiring all of the permits under subdivisions (1) through (5) of subsection (a) of this section shall not exceed five thousand eight hundred eight dollars ($5,808). Notwithstanding G.S. 143-215.3D, the maximum permit application fee to be charged for the express review of a project application requiring all of the permits under subdivisions (1) through (4) of subsection (a) of this section shall not exceed four thousand seven hundred fifty-two dollars ($4,752). Notwithstanding G.S. 143-215.3D, the maximum permit application fee charged for the express review of a project application for any other combination of permits under subdivisions (1) through (5) of subsection (a) of this section shall not exceed four thousand two hundred twenty-four dollars ($4,224). As set forth in subsection (a1) of this section, express review of a project application involving additional permits or certifications issued by the Department of Environmental Quality other than those under subdivisions (1) through (5) of subsection (a) of this section may be allowed by the Department, and, notwithstanding G.S. 143-215.3D or any other statute or rule that sets a permit fee, the maximum permit application fee charged for the express review of a project application that includes a permit, approval, or certification designated for express review under subsection (a1) of this section shall not exceed four thousand two hundred twenty-four dollars ($4,224), plus one hundred fifty percent (150%) of the fee that would otherwise apply by statute or rule for that particular permit, approval, or certification. Additional fees, not to exceed fifty percent (50%) of the original permit application fee under this section, may be charged for subsequent reviews due to the insufficiency of the permit applications. The Department of Environmental Quality may establish the procedure by which the amount of the fees under this subsection is determined, and the fees and procedures are not rules under G.S. 150B-2(8a) for the express review program under this section."
SECTION 9.(b) G.S. 143B-279.20 reads as rewritten:
"§ 143B-279.20. Report on Department activity to process applications for permits required for natural gas pipelines and gas-fired electric generation facilities. The Department of Environmental Quality shall report on any applications received for permits permits, authorizations, or certifications required for siting or operation of natural gas pipelines and gas-fired electric generation facilities within the State, and activities of the Department to process such applications, including tracking of processing times. The report shall also include information on all activities under the express review program required pursuant to G.S. 143B-279.13(a2). The processing time tracked shall include (i) the total processing time [removed: Senate Bill 730-Fourth Edition Page 11] from when an initial permit application is received to issuance or denial of the permit and (ii) the processing time from when a complete permit application is received to issuance or denial of the permit. The Department shall report quarterly to the Joint Legislative Commission on Energy Policy pursuant to this section."
455 words unchanged, in 11 paragraphs
SECTION 9.(c) Within 30 days of the date this section becomes law, the Department shall notify applicants for all entities with pending applications for permits, authorizations, and certifications required from the Department for projects involving the generation, distribution, or transmission of energy or fuel, including natural gas, diesel, petroleum, or electricity, of the express review program enacted by subsection (b) of this section, and shall inform the applicants of the ability to process pending applications through the program upon payment of the applicable fee pursuant to G.S. 143B-279.13(b).
SECTION 9.(d) This section is effective when it becomes law and applies to applications for permits, authorizations, and certifications pending on or submitted after that date.
REQUIRE DEVELOPMENT OF NUCLEAR RESOURCES PRIOR TO RETIREMENT
OF BASELOAD FACILITIES OR FACILITIES WITH DISPATCHABLE ELECTRIC GENERATION ABOVE 100 MW TO ENSURE ADEQUACY OF GRID
SECTION 10. G.S. 62-110.9(4) reads as rewritten:
"(4) Retain discretion to determine optimal timing and generation and resource-mix to achieve the least cost path to compliance with the authorized carbon reduction goal, including discretion in achieving the authorized carbon reduction goal by the date specified in order to allow for implementation of solutions that would have a more significant and material impact on carbon reduction; provided, however, the Commission shall not exceed the date specified to achieve the authorized carbon reduction goal by more than two years, except in the event the Commission authorizes construction of a nuclear facility or wind energy facility that would require additional time for completion due to technical, legal, logistical, or other factors beyond the control of the electric public utility, or in the event necessary to maintain the adequacy and reliability of the existing grid. In making such determinations, the Utilities Commission shall receive and consider stakeholder input. The Commission shall not authorize retirement of baseload facilities or facilities with dispatchable electric generation above 100 MW until such time as a certificate of public convenience and necessity has been issued to an electric public utility for construction of one nuclear facility with a generating capacity of at least 1,000 MW to ensure the adequacy of baseload and dispatchable generation from a clean energy resource."
PART III. MISCELLANEOUS
COOLING-OFF PERIOD FOR UTILITIES COMMISSIONERS AND STAFF
SECTION 11.(a) Article 15 of Chapter 62 of the General Statutes is amended by adding a new section to read:
"§ 62-327A. Post-employment restrictions on members and employees of Commission.
(a) Cooling-Off Period. ‒ It shall be unlawful for any former commissioner or employee of the Commission to make, with the intent to influence on behalf of an employer or client, any communication to or appearance before the Commission within a period of six months following the termination of his or her service or employment with the Commission.
(b) Penalty. ‒ A violation of this section is a Class 3 misdemeanor." [added: Senate Bill 730-Fifth Edition Page 11]
SECTION 11.(b) This section becomes effective December 1, 2026, and applies to offenses committed on or after that date.
[removed: Page 12 Senate Bill 730-Fourth Edition 2] SEVERABILITY/EFFECTIVE DATE [removed: 3]
SECTION 12. If any section or provision of this act is declared unconstitutional or [removed: 4] invalid by the courts, it does not affect the validity of this act as a whole or any part other than [removed: 5] the part so declared to be unconstitutional or invalid. [removed: 6]
SECTION 13. Except as otherwise provided, this act is effective when it becomes [removed: 7] law. [removed: Senate Bill 730-Fourth Edition Page 13]